LAKE TANGANYIKA REGIONAL FISHERIES PROGRAMME (TREFIP)

A proposal for implementation of the Lake Tanganyika
Framework Fisheries Management Plan


LAKE TANGANYIKA REGIONAL FISHERIES PROGRAMME (TREFIP)
A proposal for implementation of the Lake Tanganyika
Framework Fisheries Management Plan

Field Report F–14

Prepared by

THE JOINT AfDB/FAO/FISHCODE MISSION
C. MAGNET, J.E. REYNOLDS and H. BRU

FISHCODE/MANAGEMENT - GCP/INT/648/NOR

FAO/NORWAY GOVERNMENT
COOPERATIVE PROGRAMME

FOOD AND AGRICULTURE ORGANIZATION OF THE UNITED NATIONS
Rome, July 2000

Table of Contents


The designations employed and the presentation of material in this information product do not imply the expression of any opinion whatsoever on the part of the Food and Agriculture Organization of the United Nations concerning the legal or development status of any country, territory, city or area or of its authorities, or concerning the delimitation of its frontiers or boundaries.

All rights reserved. Reproduction and dissemination of material in this information product for educational or other non-commercial purposes are authorized without any prior written permission from the copyright holders provided the source is fully acknowledged. Reproduction of material in this information product for resale or other commercial purposes is prohibited without written permission of the copyright holders. Applications for such permission should be addressed to the Chief, Publishing Management Service, Information Division, FAO, Viale delle Terme di Caracalla, 00100 Rome, Italy or by e-mail to copyright@fao.org

© FAO 2000

This electronic document has been scanned using optical character recognition (OCR) software and careful manual recorrection. Even if the quality of digitalisation is high, the FAO declines all responsibility for any discrepancies that may exist between the present document and its original printed version.

SUMMARY

This report presents results of the joint AfDB/FAO/FISHCODE Mission to Lake Tanganyika, which was carried out between March and July 2000, and involved technical consultations at FAO Headquarters in Rome as well as extensive field visits to the Lake Tanganyika region.


TABLE OF CONTENTS


GCP/INT/648/NOR Field Report F–14(En)pdf

ACKNOWLEDGEMENTS

ABBREVIATIONS AND ACRONYMS

EXECUTIVE SUMMARY

PROGRAMME MATRIX

1. INTRODUCTION

1.1 Programme Background and History
1.2 Performance of Similar Projects in the Region

2. FISHERIES SECTOR

2.1 Generalities
2.2 Fisheries Policy and Development Institutions
2.3 Lake Tanganyika Fisheries
2.3.4 Post-harvest Sector

3. PROGRAMME AREA

3.1 Location and Physical Setting
3.2 Socio-Economic Setting
3.3 Gender Issues

4. THE PROGRAMME

4.1 Objectives
4.2 Programme outputs
4.3 Detailed description of activities and components
4.4 Programme Assumptions and Risks
4.5 Programme Costs
4.6 Sources of finance
4.7 Environmental Impacts
4.8 Impacts on Women
4.9 Impacts on Poverty Reduction

5. PROGRAMME IMPLEMENTATION

5.1 Executing Agency
5.2 Organisation and Management
5.3 Procurement of Goods and Works
5.4 Implementation Plan and Expenditure Schedule
5.5 Monitoring and Evaluation
5.6 Recurrent Costs
5.7 Programme Sustainability
5.8 Co-ordination with Other Donors

6. TECHNICAL AND ECONOMIC JUSTIFICATION

6.1 Technical Justifica
6.2 Economic Justification
6.3 Financial Justificattion

7. CONCLUSIONS AND RECOMMENDATIONS

7.1 Conclusions
7.2 Recommendations and Conditions of Loan Approval

ANNEXESpdf

ANNEX 1. MISSION TERMS OF REFERENCE

ANNEX 2. MISSION ITINERARY

ANNEX 3. MISSION MEETINGS/PERSONS MET

ANNEX 4. REFERENCES CITED/CONSULTED

ANNEX 5. TERMS OF REFERENCE, CIFA SUB-COMMITTEE FOR LAKE TANGANYIKA

ANNEX 6. MARKETING AND PRICES, LAKE TANGANYIKA FISHERIES

ANNEX 7. CREDIT PROFILES, LAKE TANGANYIKA FISHERIES

ANNEX 8. TREFIP COMPONENT PROJECT PROFILES

ANNEX 8.1 REGIONAL PROGRAMME IMPLEMENTATION UNIT/ HEADQUARTERS
ANNEX 8.2 BURUNDI NATIONAL PROJECT COMPONENT
ANNEX 8.3 D.R. CONGO NATIONAL PROJECT COMPONENT
ANNEX 8.4 TANZANIA NATIONAL PROJECT COMPONENT
ANNEX 8.5 ZAMBIA NATIONAL PROJECT COMPONENT

ANNEX 9. PROGRAMME COSTS

ANNEX 10. PREPARATORY PHASE

ANNEX 11. PROGRAMME ECONOMIC ANALYSIS

ANNEX 12. PROGRAMME FUNDING PROPOSAL