Item | Unit | Qty. | Unit price | Cost (FJD) | Total cost (FJD) | |||
---|---|---|---|---|---|---|---|---|
1. Office building | ||||||||
Foundation: concrete footing 500 mm below ground surface 400 mm width. | m2 | 200 | 600 | 120 000 | 120 000 | |||
Floor: 150 mm concrete on sandy gravel bedding with moisture insulation. | ||||||||
Walls: concrete block 150 mm with two side plastering. | ||||||||
Standard roofing, corrugated iron sheet, with heat insulation, and ventilation. | ||||||||
Internal division (number of rooms) appropriate to accommodate 10 staff members with meeting room, tea room with separate entry from the yard, lecture room approx. for 20 persons with separate entry from the yard. | ||||||||
Building complete with electrical and sanitary installations (toilets for gents and ladies two each, cold and warm water supply water heater min. 200 l storage capacity, shower for gents and ladies one each. | ||||||||
Cost includes material and labour. | ||||||||
2. Laboratory building | ||||||||
Foundation: concrete footing 500 mm below ground surface 400 mm width. | m2 | 100 | 600 | 60 000 | 60 000 | |||
Floor: 150 mm concrete on sandy gravel bedding with moisture insulation. | ||||||||
Walls: concrete block 150 mm with two side plastering. | ||||||||
Standard roofing, corrugated iron sheet, with heat insulation, and ventilation. | ||||||||
One main door 2100 mm × 1000 mm, and two doors to hatcheries 2100 mm × 1500 mm. Windows on longer sides. | ||||||||
Inside separate room, approx 6 m2 for storage. | ||||||||
Building complete with electrical and sanitary installations (toilets for gents and ladies one each, cold and warm water supply, water heater min. 80 l storage capacity). | ||||||||
Cost includes material and labour | ||||||||
3. Feed mill and store | ||||||||
Foundation: concrete footing 500 mm below ground surface 400 mm width. | m2 | 180 | 420 | 75 600 | 76 000 | |||
Floor: 200 mm concrete on sandy gravel bedding with moisture insulation. | ||||||||
Walls: concrete block 150 mm with two side plastering. | ||||||||
Standard roofing, corrugated iron sheet, with ventilation. | ||||||||
Internal division for feed store 50 m3 with heat insulation. | ||||||||
Building complete with 3 phase electric supply. | ||||||||
Cost includes material and labour. | ||||||||
4. Equipment store | ||||||||
Foundation: concrete footing 500 mm below ground surface 400 mm width. | m2 | 120 | 350 | 42 000 | 42 000 | |||
Floor: 150 mm concrete on sandy gravel bedding with moisture insulation. | ||||||||
Walls: concrete block 150 mm with two side plastering. | ||||||||
Standard roofing, corrugated iron sheet, with ventilation and insulation. Building complete with electric supply. | ||||||||
Cost includes material and labour. | ||||||||
5. Workshop and shed | ||||||||
5.1 | Workshop | m2 | 70 | 600 | 42 000 | |||
Standard local building and equipment. | ||||||||
Foundation: concrete footing 500 mm below ground surface 400 mm width. | ||||||||
Floor: 200 mm concrete on sandy gravel bedding with moisture insulation. | ||||||||
Walls: concrete block 150 mm with two side plastering. | ||||||||
Standard roofing, corrugated iron sheet, with ventilation and insulation. | ||||||||
Building complete with 3 phase electric supply. | ||||||||
Internal division: 1 store room. | ||||||||
Cost includes material and labour. | ||||||||
5.2 | Shed | m2 | 240 | 400 | 96 000 | |||
Standard for machine protection, concrete floor, pine post and corrugated iron roofing on timber truss. Timber treated to climatic conditions. | ||||||||
Workshop and open shed total: | 138 000 | 138 000 | ||||||
6. Dormitory | ||||||||
Foundation: concrete footing 500 mm below ground surface 400 mm width. | m2 | 200 | 1 000 | 200 000 | 200 000 | |||
Floor: 150 mm concrete on sandy gravel bedding with moisture insulation. | ||||||||
Walls: concrete block 150 mm with two side plastering. | ||||||||
Standard roofing, corrugated iron sheet, with heat insulation, and ventilation. | ||||||||
Internal division (number of rooms) appropriate to accommodate 20 guests. | ||||||||
Building complete with electrical and sanitary installations (toilets for gents and ladies three each, cold and warm water supply water heater min. 200 l storage capacity, shower for gents and ladies two each) and kitchen / dining. | ||||||||
Cost includes material and labour | ||||||||
7. Tilapia / carp hatchery | ||||||||
7.1 | Shed | m2 | 155 | 450 | 69 750 | |||
Foundation: concrete footing 500 mm below ground surface 400 mm width. | ||||||||
Floor: 200 mm concrete 20 Mpa on sandy gravel bedding with moisture insulation. | ||||||||
Walls against wind made of 100 mm concrete blocks on two sides of shed 27 m in length, 2.30 m height with one door 2100 mm × 1500 mm, steel mesh up the ceiling level. | ||||||||
Roof: timber trusses with corrugated iron sheet cover on pine posts. Timber treated to climatic conditions. | ||||||||
Cost includes material and labour | ||||||||
7.2 | Water supply within hatchery | |||||||
7.2.1 | Overhead tank outdoor, fibreglass on pine posts, 2.8 m3 storage capacity, incl. drain valve and floating ball valve. | pc | 1 | 2 000 | 2 000 | |||
7.2.2 | Internal piping, main pipe diam. 100 mm, length 50 m with bends, tees, and valves for sectioning | m | 50 | 15 | 750 | |||
7.2.3 | PVC distribution pipes for devices diam. 50 mm, 3m/device incl. 1 globe valve per branching and 1m 3/4" flexible (polythene) pipe with globe valve per device. | pc | 12 | 30 | 360 | |||
Sub-total water supply: | 3 110 | |||||||
7.3 | Air supply | |||||||
7.3.1 | Internal piping, air distribution diam. 50 mm, length 50 m with bends, tees, and valves for sectioning | m | 50 | 8 | 400 | |||
7.3.2 | Air distribution pipes for devices diam. 50 mm, 3m/device incl. 1 valve per branching and 1 m 3/4" pipe with globe valve per device | pc | 9 | 30 | 270 | |||
7.3.3 | Biofilters, airstones, immerse water heaters and other miscellaneous items | 10 000 | ||||||
Sub-total air supply: | 10 670 | |||||||
7.4 | Drainage within hatchery | |||||||
7.4.1 | Floor drain U shaped 20 Mpa concrete 0.12 m3/m, with light reinforcement diam 8 mm, 32 kg/m and steel grate, cover 11 kg/m. | m | 33 | 280 | 9 240 | |||
7.4.2 | Cleaning shaft 0.32 m3 concrete with 665 wire mesh reinforcement, and chequerplate cover. | pc | 1 | 200 | 200 | |||
Sub-total drainage: | 9 440 | |||||||
7.5 | Technological devices | |||||||
7.5.1 | 20 litre fibre glass hatching unit. | |||||||
7.5.1.1 | 20 litre jars. | pc | 10 | 500 | 5 000 | |||
7.5.1.2 | Fibreglass drain troughs. | pc | 1 | 500 | 500 | |||
7.5.1.3 | Distribution pipe, PVC 2.08 m × 150 mm diam, 13 pc branching ID 20 with globe valve (screwed with union). | pc | 1 | 250 | 250 | |||
7.5.1.4 | Steel stand rounded steel bars diam 12 – 24 mm. | kg | 72 | 6 | 432 | |||
Sub-total 20 litre jars 1 block: | 6 182 | |||||||
7.5.2 | 60 litre fibre glass hatching / rearing unit | |||||||
7.5.2.1 | 60 litre jars. | pc | 8 | 800 | 6 400 | |||
7.5.2.2 | Fibreglass drain troughs. | pc | 1 | 500 | 500 | |||
7.5.2.3 | Distribution pipe, PVC 2.08 m × 150 mm diam, 11 pc branching ID 20 with globe valve (screwed with union). | pc | 1 | 230 | 230 | |||
7.5.2.4 | Steel stand rounded steel bars diam 12 – 24 mm. | kg | 80 | 6 | 480 | |||
Sub-total 60 litre jars 1 block: | 7 610 | |||||||
7.5.3 | 200 litre fibre glass hatching / rearing unit | |||||||
7.5.3.1 | 200 l jars. | pc | 4 | 1 400 | 5 600 | |||
7.5.3.2 | Fibreglass drain trough. | pc | 1 | 500 | 500 | |||
7.5.3.3 | Distribution pipe, PVC 2.08 m × 150 mm diam, 7 pc branching ID 20 with globe valve (screwed with union). | pc | 1 | 190 | 190 | |||
7.5.3.4 | Steel stand rounded steel bars diam 12 – 26 mm. | kg | 174 | 6 | 1 044 | |||
Sub-total 200 litre jars 1 block: | 7 334 | |||||||
7.5.4 | 75 litre fibre glass rearing trough unit. | |||||||
7.5.4.1 | 75 litre fibre glass rearing trough. | pc | 4 | 500 | 2 000 | |||
7.5.4.2 | Steel stand rounded steel bars diam 12 – 26 mm. | kg | 80 | 6 | 480 | |||
Sub-total 75 litre trough 1 block: | 2 480 | |||||||
Sub-total 75 litre trough 4 blocks: | 9 920 | |||||||
7.5.5 | Concrete tanks 2 × 1,3 m3 | |||||||
7.5.5.1 | Concrete slab and walls 20 Mpa. | m3 | 2 | 360 | 828 | |||
7.5.5.2 | 665 wire mesh at base slab. | m2 | 4 | 6 | 24 | |||
7.5.5.3 | Vertical reinforcement, diam 12 mm. | kg | 90 | 3 | 270 | |||
7.5.5.4 | Form work. | m2 | 20 | 36 | 720 | |||
7.5.5.5 | Turn-down pipe diam 50 PVC. | pc | 2 | 6 | 12 | |||
Sub-total c.c. tank 2×1.3 m3 1 block: | 1 854 | |||||||
Sub-total c.c. tank 2×1.3 m3 4 blocks: | 7 416 | |||||||
7.5.6 | Concrete tanks 2 × 2,6 m3 | |||||||
7.5.6.1 | Concrete slab and walls 20 Mpa. | m3 | 4 | 360 | 1 368 | |||
7.5.6.2 | 665 wire mesh at base slab. | m2 | 9 | 6 | 51 | |||
7.5.6.3 | Vertical reinforcement, diam 12 mm. | kg | 120 | 3 | 360 | |||
7.5.6.4 | Form work. | m2 | 32 | 36 | 1 152 | |||
7.5.6.5 | Turn-down pipe diam 50 PVC. | pc | 2 | 6 | 12 | |||
Sub-total c.c. tank 2×2.6 m3 1 block: | 2 943 | |||||||
Sub-total c.c. tank 2×2.6 m3 4 blocks: | 11 772 | |||||||
Sub-total technological devices: | 50 234 | |||||||
Tilapia / carp hatchery total: | 143 204 | 144 000 | ||||||
8. Prawn hatchery unit | ||||||||
8.1 | Shed. | m2 | 170 | 450 | 76 500 | |||
Foundation: concrete footing 500 mm below ground surface 400 mm width. | ||||||||
Floor: 200 mm concrete 20 Mpa on sandy gravel bedding with moisture insulation. | ||||||||
Walls against wind made of 100 mm concrete blocks on two sides of shed 28 m in length, 2.30 m height, galvanised steel mesh up to the ceiling level. | ||||||||
Roof: timber trusses with corrugated iron sheet cover on pine posts. Timber treated to climatic conditions. | ||||||||
Cost includes material and labour | ||||||||
8.2 | Water supply within hatchery | |||||||
8.2.1 | Overhead tank outdoor, fibreglass on pine posts, 3 m3 storage capacity, one-one for fresh and salt water incl drain valve and floating ball valve. | pc | 2 | 2 000 | 4 000 | |||
8.2.2 | Internal piping, main pipe for freshwater diam. 100 mm, length 50 m with bends, tees, and valves for sectioning | m | 50 | 15 | 750 | |||
8.2.4 | PVC freshwater distribution pipes for devices diam. 50 mm, 3m/device incl. 1 globe valves per branching and 1m 3/4" flexible pipe with globe valve per device | pc | 9 | 30 | 270 | |||
Sub-total water supply: | 5 020 | |||||||
8.3 | Air supply | |||||||
8.3.1 | Internal piping, air distribution diam. 50 mm, length 50 m with bends, tees, and valves for sectioning | m | 50 | 8 | 400 | |||
8.3.2 | Air distribution pipes for devices diam. 50 mm, 3m/device incl. 1 valve per branching and 1m 3/4" flexible pipe with globe valve per device | pc | 9 | 30 | 270 | |||
8.3.3 | Biofilters, airstones, immerse water heaters and other miscellaneous items | 10 000 | ||||||
8.3.4 | Air blower | 5 000 | ||||||
8.3.5 | Diesel engine | 5 000 | ||||||
Sub-total air supply: | 20 670 | |||||||
8.4 | Drainage within hatchery | |||||||
8.4.1 | Floor drain U shaped 20 Mpa concrete 0.12 m3/m, with light reinforcement diam 8 mm, 32 kg/m and steel grate, cover 11 kg/m | m | 33 | 280 | 9 240 | |||
8.4.2 | Cleaning shaft 0.32 m3 concrete with 665 wire mesh reinforcement, and chequerplate cover | pc | 1 | 200 | 200 | |||
Sub-total drainage: | 9 440 | |||||||
8.5 | Technological devices | |||||||
8.5.1 | Concrete tanks 2 × 1,3 m3 | block | 6 | 1 854 | 11 124 | |||
Sub-total technological devices | 11 124 | |||||||
Prawn hatchery total: | 122 754 | 123 000 | ||||||
9. Out-door concrete tanks | ||||||||
9.1 | 20 m3 rectangular tank | |||||||
9.1.1 | Concrete slab 20 Mpa. | m3 | 4 | 360 | 1 368 | |||
9.1.2 | Concrete block walls, 150 mm blocks, material and labour. | m2 | 20 | 14 | 280 | |||
9.1.3 | 665 wire mesh at base slab. | m2 | 24 | 9 | 216 | |||
9.1.4 | Vertical reinforcement, diam 12 at 400 mm centre to centre in both direction. | kg | 85 | 6 | 510 | |||
9.1.5 | Plastering, both side water tight 10 mm. | m2 | 48 | 12 | 576 | |||
9.1.6 | Turn-down pipe diam 50 PVC. | pc | 1 | 6 | 6 | |||
Total for 1 rectangular tank: | 2 956 | |||||||
Total for 24 rectangular tanks: | 70 944 | |||||||
9.2 | Circular tank | |||||||
9.2.1 | Concrete slab 20 Mpa. | m3 | 6 | 360 | 2 160 | |||
9.2.2 | Concrete block walls, 150 mm blocks, material and labour. | m2 | 23 | 14 | 322 | |||
9.2.3 | 665 wire mesh at base slab. | m2 | 19 | 9 | 171 | |||
9.2.4 | Vertical reinforcement, diam 12 in 400 mm centre to centre in both direction. | kg | 82 | 6 | 492 | |||
9.2.5 | Plastering, both side water tight, 10 mm thick. | m2 | 46 | 12 | 552 | |||
9.2.6 | Turn-down pipe diam 50 PVC. | pc | 1 | 6 | 6 | |||
Total for 1 circular tank: | unit | 1 | 3 703 | |||||
Out-door tanks total: | 74 647 | 75 000 | ||||||
10. Quarantine facilities | ||||||||
10.1 | 20 m3 rectangular tank. | block | 8 | 2 956 | 23 648 | |||
10.2 | Septic tank. | pc | 1 | 5 000 | 5 000 | |||
Quarantine facilities total: | 28 648 | 29 000 | ||||||
11. Earthwork | ||||||||
11.1 | Removal of top soil in 0.20 m thickness and depositing. | m2 | 100 000 | 2 | 200 000 | |||
11.2 | Excavation and dike filling. Estimated excavation is one third of the pond depth × pond surface area. (5.81 ha × 1.50 m/3). Dike filling in layers and compaction. | m3 | 30 000 | 7 | 210 000 | |||
11.3 | Excavation of drainage canals and seepage trenches, dressing of banks and ground surface. Excavated earth built into dikes. | m3 | 4 500 | 7 | 31 500 | |||
11.4 | Laying of removed top soil over dikes, pond bottom and exposed ground surface in 0.20 m thickness. | m3 | 10 000 | 15 | 150 000 | |||
Earthworks total: | 591 500 | 592 000 | ||||||
12. Pond structures | ||||||||
12.1 | Drainage structures | |||||||
12.1.1 | Earth work: excavation across dike, rehandling, backfilling following concrete works, compaction, dressing of banks and ground surface. | m3 | 12 | 12 | 144 | |||
12.1.2 | 20 Mpa concrete, including cement, gravel shuttering, curing, rendering and finishing exposed surface, but excluding reinforcement. | m3 | 3 | 240 | 720 | |||
12.1.3 | Reinforcement: material and labour. | kg | 40 | 6 | 240 | |||
12.1.4 | Blinding layer 50 mm, 10 Mpa, material and labour. | m3 | 0,20 | 100 | 20 | |||
12.1.5 | Lining around structures: 300 mm × 300 mm × 80 mm c.c. slabs on 5 cm sandy gravel bedding, material and labour. | m2 | 10 | 15 | 150 | |||
12.1.6 | Control boards, 12 mm marine ply board, 8 × 470 mm × 250 mm. | m2 | 8 | 5 | 40 | |||
12.1.7 | Steel screens 470 mm × 250 mm. | pc | 4 | 12 | 48 | |||
12.1.8 | Concrete pipe ID 300 laid on 200 mm × 50 mm sandy gravel bedding including material and labour | m | 13 | 150 | 1 950 | |||
Sub-total 1 drainage structure: | 3 312 | |||||||
Sub-total 78 drainage structures: | 258 336 | |||||||
12.2 | Culverts | |||||||
12.2.1 | Earth work: excavation across dike, rehandling, backfilling following concrete works, compaction, dressing of banks and ground surface | m3 | 16 | 12 | 192 | |||
12.2.2 | 20 Mpa concrete, including cement, gravel shuttering, curing, rendering and finishing exposed surface, but excluding reinforcement | m3 | 1 | 240 | 240 | |||
12.2.3 | Reinforcement: material and labour | kg | 20 | 6 | 120 | |||
12.2.4 | Blinding layer 50 mm, 10 Mpa, material and labour | kg | 0,10 | 100 | 10 | |||
12.2.5 | Lining around structures: 300 mm × 300 mm × 80 mm c.c. slabs on 50 mm sandy gravel bedding, material and labour | m2 | 8 | 15 | 120 | |||
12.2.6 | Concrete pipe ID 300 laid on 150 × 50 mm sandy gravel bedding including material and labour | m | 15 | 150 | 2 250 | |||
Sub-total 1 culvert: | 2 932 | |||||||
Sub-total 3 culverts: | 8 796 | |||||||
Pond structures total | 267 132 | 268 000 | ||||||
13. Water supply to hatcheries | ||||||||
13.1 | Construction of elevated reservoir, 5 m3, 20 Mpa concrete with reinforcement. | pc | 1 | 6 000 | 6 000 | |||
13.2 | Pipe between reservoir and elevated reservoir | |||||||
13.2.1 | Earthwork: excavation of trench, and backfilling after pipe laying incl. compaction 1,200 m, 0.3 m3/m. | m3 | 360 | 12 | 4 320 | |||
13.2.2 | Pipe laying, PVC diam 200, material and labour. | m | 1 200 | 45 | 54 000 | |||
13.3 | Pipe between elevated reservoir and hatcheries | |||||||
13.3.1 | Earthwork: excavation of trench, and backfilling after pipe laying incl. compaction 260 m, 0.3 m3/m. | m3 | 78 | 12 | 936 | |||
13.3.2 | Pipe laying, PVC diam 200, material and labour. | m | 260 | 45 | 11 700 | |||
Water supply total: | 76 956 | 77 000 | ||||||
14. Pond water supply | ||||||||
14.1 | Check dam on irrigation canal, construction. | pc | 1 | 1 000 | 1 000 | |||
14.2 | Diversion sluice, construction, complete with aluminium gate | pc | 1 | 10 000 | 10 000 | |||
14.3 | Filter pond 15 × 10 m, construction, complete. | m3 | 200 | 7 | 1 400 | |||
14.4 | Outlet structure in filter pond for pipes | pc | 1 | 5 000 | 5 000 | |||
14.5 | Pipe network to ponds: earthwork: excavation of trench, and backfilling after pipe laying incl. compaction 0.3 m3/m | m3 | 600 | 12 | 7 200 | |||
14.6 | Pipe network to ponds, PVC diam 200 | m | 2 000 | 45 | 90 000 | |||
Total pond water supply | 114 600 | 115 000 | ||||||
15. Water (drinking) supply to site | ||||||||
Construction of drinking water supply main to site from nearest existing main (approx 500 m). | m | 500 | 50 | 25 000 | 25 000 | |||
16. Sewage works of the centre | ||||||||
16.1 | Septic tank, standard, 20 m3 as per health requirements | pc | 1 | 5 000 | 5 000 | |||
16.2 | Pipe network between buildings and to septic tank: excavation of trench, and backfilling after pipe laying incl. compaction 0.3 m3/m | m3 | 300 | 72 | 21 600 | |||
16.3 | Pipe laying: material and labour, diam 200 | m | 300 | 25 | 7 500 | |||
Sewage works total | 34 100 | 35 000 | ||||||
17. Electric supply | ||||||||
Installation of 3 phase electricity transmission line and transformer, erection of posts, cabling complete. | 100 000 | 100 000 | ||||||
18. Telephone line | ||||||||
Installation of telephone lines to site, 3 lines, erection of posts and cabling. | line | 3 | 10 000 | 30 000 | 30 000 | |||
19. Road improvement | ||||||||
19.1 | Road improvement 150 mm gravel bedding 3,5 m wide, 500 m length. | m3 | 600 | 25 | 15 000 | |||
19.2 | Construction of culvert crossing at section 2150 m of irrigation canal. | pc | 1 | 10 000 | 10 000 | |||
Road improvement total: | 25 000 | 25 000 | ||||||
20. Fencing | ||||||||
Chainlink fencing around site on pine posts 1,8 m height, material and labour. | m | 2 200 | 20 | 44 000 | 44 000 | |||
21. Miscellaneous | ||||||||
Guard house, site illumination, security lights, yard development, etc. | 100 000 | 100 000 | ||||||
22. Reserve approx. 10 % | 231 800 | 232 000 | ||||||
Grand Total Excluding Residential Buildings | 2 650 000 | |||||||
(Rounded to FJD 100,000) | 2 700 000 | |||||||
23. Residential buildings | ||||||||
Government standard size and installations (for officials, researchers, administrative and labour staff), incl. fencing. | pc | 30 | 50 000 | 1 500 000 | 1 500 000 | |||
Grand Total Including Residential Buildings | 4 700 000 |