Previous PageTable Of ContentsNext Page

ORGANIZATIONAL PERFORMANCE

19. It should be noted that while the Programme Implementation Report (PIR) draws information from the unaudited FAO financial accounts1 and the underlying accounting records in setting out details of resources and expenditures, for the most part it is not intended to be an accounting document.

20. Information provided in this section of the report includes evolution of resources, the cost of field programme support, the extent of technical support provided to the field programme by FAO technical officers, a progress report on the implementation of FAO's language policy, personnel developments and summary information on outputs. Further analysis of the implementation of outputs specified for the technical programmes in the Programme of Work and Budget (PWB) 2000-01 is provided at programme level in the next section of the PIR on Summary of Programme Implementation. Detailed information on all of the outputs in the PWB 2000-01 and the status of their implementation has been placed on the FAO Internet site at http://www.fao.org/pir .

EVOLUTION OF TOTAL RESOURCES

21. Expenditure in 2000-01, as reported in the financial accounts for 2000-01 by source of funds, is presented in Table 2.1 under the accounting categories of General and Related Funds and Trust Funds and the United Nations Development Programme (UNDP):

TABLE 2.1. EXPENDITURE SUMMARY BY SOURCE OF FUNDS (US$ MILLION)

Funding source

1998-99

2000-01

General and Related Funds

   

Regular Programme appropriation (verses budget of US$650 million)

648.8

638.3

Jointly financed investment activities

24.2

22.9

Trust Fund support cost reimbursements

28.1

26.5

UNDP support cost reimbursements

4.7

2.6

Currency variance on staff cost

(10.5)

(24.0)

Other*

0.1

3.5

Subtotal

695.4

669.8

Trust Funds and UNDP

   

Trust Funds (excluding emergency projects)

271.8

275.2

Special relief operations (emergency projects)

175.0

325.3

UNDP

57.4

33.8

Subtotal

504.2

634.3

Total expenditures

1,199.6

1,304.1

* Includes items such as the 2000-01 expenditure against the 1998-99 Technical Cooperation Programme (TCP) appropriation, adjusted by the unspent TCP appropriation from 2000-01 which can be spent in 2002-03, financial services provided to WFP, the expenditure of the Information Products Revolving Fund and government cash counterpart contributions to country offices.

22. Total expenditure in 2000-01 was US$1,304 million, US$105 million (8.7 percent) higher than 1998-99. Expenditure levels of the past two biennia are illustrated in Figure 2.1.

23. The 2000-01 programme of work included the projected availability of resources from other income, which comprises voluntary contributions that are largely at the disposal of the Organization and managed closely with the regular budget appropriation. The inclusion of other income in the programme of work provides a more complete picture of the resources associated with the work being undertaken. However, changes in income versus the budgeted levels during programme implementation require corresponding changes in expenditures in order to conform to the approved budgetary appropriation, adding some uncertainty and complexity to the financial management of the budgetary appropriation.

24. Expenditures to implement the programme of work versus the final 2000-01 budget are shown in Table 2.2. Expenditure totalled US$705.52 million against a corresponding budget of US$725.2 million. Income earned was US$67.2 million against an income target of US$75.2 million, a shortfall of US$8 million. Overall net expenditure against the Regular Programme appropriation of US$650 million was US$638.4 million.

25. Significant shortfalls in income occurred under Major Programme 3.2: Support to Investment, mainly the result of FAO/World Bank Cooperative Programme income projections which did not materialize, Major Programme 3.3: Field Operations and Chapter 6: Common Services, where support cost reimbursements from Trust Funds and UNDP were less than projected. In many programmes, the shortfall in income reimbursements was mitigated by a positive staff cost variance and avoided the need for the transfer between chapters of the PWB, which in the past has often been required.

26. The staff cost variance is the difference between budgeted and actual staff costs in a biennium. For the 2000-01 biennium there was a positive staff cost variance of US$21.3 million. The main reasons for the positive variance were presented to the Finance Committee in September 2001 and indicated that the favourable result for the biennium arose from the combination of several distinct factors:

27. Staff cost variance was closely monitored during the 2000-01 biennium and some additional divisional allotments for high-priority activities were provided in a planned fashion, mainly to the technical departments, when the estimated surplus warranted such action. However, as the staff cost variance was sensitive to matters outside the Organization's direct control, prudence was required in committing additional funds against a forecasted positive variance.

28. Most of the underlying causes of difference between the actual and standard unit costs of staff are beyond the control of the allottees and depend, for example, on exchange rates at non-headquarters locations, decisions of the International Civil Service Commission, and so on. Therefore, in the summary tables preceding each programme in the summary of programme implementation section of the PIR, information is provided on expenditure both before and after staff cost variance.

TABLE 2.2. BUDGETARY PERFORMANCE, 2000-01 (US$ 000)

   

2000-01 Budget

2000-01 Expenditure

Variance: Budget less Expenditure/Income

CH/MP

Description

Programme
of Work

Income

Appropriation

Gross
Expenditure

Income

Net
Expenditure

Programme
of Work
(Over)/under

Income
Over/(under)

Appropriation
Over/(under)

1.1

Governing Bodies

17,671

0

17,671

17,230

(21)

17,209

441

21

462

1.2

Policy, Direction and Planning

22,479

(2,751)

19,728

21,373

(2,330)

19,043

1,106

(421)

685

1.3

External Coordination and Liaison

12,703

0

12,703

11,882

0

11,882

821

0

821

1.9

Programme Management

789

0

789

867

0

867

(78)

0

(78)

Ch. 1

General Policy and Direction

53,642

(2,751)

50,891

51,352

(2,351)

49,001

2,290

(400)

1,890

2.1

Agricultural Production and Support Systems

89,378

(1,279)

88,099

86,912

(1,761)

85,151

2,466

482

2,948

2.2

Food and Agriculture Policy and Development

86,080

(518)

85,562

83,389

(714)

82,675

2,691

196

2,887

2.3

Fisheries

39,221

(675)

38,546

38,113

(488)

37,625

1,108

(187)

921

2.4

Forestry

30,448

(740)

29,708

30,520

(661)

29,859

(72)

(79)

(151)

2.5

Contributions to Sustainable Development and Special Programme Thrusts

48,477

(1,215)

47,262

48,278

(650)

47,628

199

(565)

(366)

Ch. 2

Technical and Economic Programmes

293,604

(4,427)

289,177

287,212

(4,274)

282,938

6,392

(153)

6,239

3.1

Policy Assistance

27,036

(841)

26,195

25,802

(734)

25,068

1,234

(107)

1,127

3.2

Support to Investment

46,546

(27,707)

18,839

45,094

(25,942)

19,152

1,452

(1,765)

(313)

3.3

Field Operations

20,987

(16,034)

4,953

18,836

(13,546)

5,290

2,151

(2,488)

(337)

3.4

FAO Representatives

72,403

(8,737)

63,666

69,370

(8,240)

61,130

3,033

(497)

2,536

3.5

Cooperation with External Partners

8,786

(2,458)

6,328

9,592

(1,946)

7,646

(806)

(512)

(1,318)

3.9

Programme Management

882

(227)

655

1,465

(149)

1,316

(583)

(78)

(661)

Ch. 3

Cooperation and Partnerships

176,640

(56,004)

120,636

170,159

(50,557)

119,602

6,481

(5,447)

1,034

4.1

Technical Cooperation Programme

89,118

0

89,118

89,025

0

89,025

93

0

93

4.2

TCP Unit

2,337

0

2,337

2,414

0

2,414

(77)

0

(77)

Ch. 4

Technical Cooperation Programme

91,455

0

91,455

91,439

0

91,439

16

0

16

5.1

Information and Publications Support

16,560

0

16,560

16,678

(50)

16,628

(118)

50

(68)

5.2

Administration

47,915

(7,156)

40,759

46,787

(6,324)

40,463

1,128

(832)

296

Ch. 5

Support Services

64,475

(7,156)

57,319

63,465

(6,374)

57,091

1,010

(782)

228

Ch. 6

Common Services

44,790

(4,868)

39,922

41,444

(3,636)

37,808

3,346

(1,232)

2,114

Ch. 7

Contingencies

600

0

600

476

0

476

124

0

124

 

TOTAL

725,206

(75,206)

650,000

705,547

(67,192)

638,355

19,659

(8,014)

11,645

29. The total of expenditures under the main chapters of the PWB are summarized in Figure 2.2. The technical work of the Organization accounted for 78 percent of expenditure in 2000-01, distributed as follows:

30. The share of expenditure between headquarters and the decentralized offices is shown in Figure 2.3. Headquarters accounted for 65 percent of total expenditures in 2000-01, down from 68 percent in 1998-99. Regular Programme funded field programme expenditures for the Technical Cooperation Programme (TCP) and the Special Programme for Food Security (SPFS) increased to 12 percent in 2000-01 from 10 percent in 1998-99 and FAORs increased to 9 from 8 percent. Regional Offices remained at 10 percent, Subregional Offices at 3 percent and Liaison Offices at 1 percent. As these figures show, headquarters remains the dominant source of expenditures for the Organization, despite the extensive decentralization that has taken place since 1994.

31. A breakdown of expenditure in relation to Chapter 2: Technical and Economic Programmes is shown in Table 2.3. The Major Programmes ended the biennium with a surplus of US$6.4 million, utilizing 97.8 percent of the resources approved in the PWB. The surplus would have been substantially higher, given the distribution of US$8.1 million of the staff cost variance to this chapter. However, once the magnitude of the positive staff cost variance became known in the latter part of the biennium, and in view of the wishes of the governing bodies to give priority to the technical and economic programmes, a substantial portion of the available funds was redirected to the technical programmes in Chapter 2. This had the result of reducing the surplus balance and, in the case of Major Programme 2.4: Forestry, resulted in the final expenditure exceeding the resource level of the programme of work.

TABLE 2.3. BUDGETARY PERFORMANCE FOR CHAPTER 2:TECHNICAL AND ECONOMIC PROGRAMMES, 2000-01 (US$ 000)

MP/PR

Description

Programme
of Work

Expenditure
Before SCV

Staff Cost
Variance

Expenditure

Over/(Under)
Spending

Field
Programme

2.1.1

Natural Resources

16,005

15,488

(400)

15,088

(917)

39,457

2.1.2

Crops

25,077

25,599

(605)

24,994

(83)

324,300

2.1.3

Livestock

16,873

17,704

(441)

17,263

390

85,871

2.1.4

Agricultural Support Systems

15,186

14,618

(421)

14,197

(989)

12,368

2.1.5

Agricultural Applications of Isotopes and Biotechnology

5,689

5,329

(35)

5,294

(395)

598

2.1.9

Programme Management

10,548

10,411

(335)

10,076

(472)

0

2.1

Agricultural Production and Support Systems

89,378

89,149

(2,237)

86,912

(2,466)

462,594

2.2.1

Nutrition

16,083

15,729

(268)

15,461

(622)

9,928

2.2.2

Food and Agricultural Information

34,164

33,799

(1,185)

32,614

(1,550)

11,175

2.2.3

Food and Agricultural Monitoring, Assessments and Outlooks

12,899

13,648

(453)

13,195

296

8,824

2.2.4

Agriculture, Food Security and Trade Policy

14,194

14,017

(439)

13,578

(616)

6,578

2.2.9

Programme Management

8,740

8,888

(347)

8,541

(199)

0

2.2

Food and Agriculture Policy and Development

86,080

86,081

(2,692)

83,389

(2,691)

36,505

2.3.1

Fisheries Information

6,406

6,694

(327)

6,367

(39)

2,935

2.3.2

Fisheries Resources and Aquaculture

10,477

10,479

(286)

10,193

(284)

12,730

2.3.3

Fisheries Exploitation and Utilization

7,956

8,002

(208)

7,794

(162)

5,025

2.3.4

Fisheries Policy

9,313

9,248

(216)

9,032

(281)

8,590

2.3.9

Programme Management

5,069

4,944

(217)

4,727

(342)

0

2.3

Fisheries

39,221

39,367

(1,254)

38,113

(1,108)

29,280

2.4.1

Forest Resources

8,254

9,019

(170)

8,849

595

26,534

2.4.2

Forest Products

4,694

4,910

(136)

4,774

80

3,302

2.4.3

Forestry Policy and Planning

8,557

8,748

(241)

8,507

(50)

32,076

2.4.4

Forest Programmes Coordination and Information

3,826

3,764

(118)

3,646

(180)

430

2.4.9

Programme Management

5,117

4,921

(177)

4,744

(373)

0

2.4

Forestry

30,448

31,362

(842)

30,520

72

62,342

2.5.1

Research, Natural Resources Management and Technology Transfer

17,655

17,591

(410)

17,181

(474)

16,760

2.5.2

Women and Population

5,367

5,641

(129)

5,512

145

7,316

2.5.3

Rural Development

8,209

7,921

(183)

7,738

(471)

16,174

2.5.6

Food Production in Support of Food Security in LIFDCs

10,270

11,577

(77)

11,500

1,230

26,764

2.5.9

Programme Management

6,976

6,636

(289)

6,347

(629)

0

2.5

Contributions to Sustainable Development and Special Programme Thrusts

48,477

49,366

(1,088)

48,278

(199)

67,014

 

TOTAL

293,604

295,325

(8,113)

287,212

(6,392)

657,735

32. The final column of Table 2.3 shows expenditure under the field programme, which comprises all technical assistance and emergency assistance activities funded through extrabudgetary sources, and Regular Programme funded technical assistance and emergency projects under the TCP and SPFS. Attention is drawn to the distinction between extrabudgetary resources, which refer to all non-Regular Programme sources of funds and related expenditures in the financial accounts of the Organization, and the field programme, which refers to the expenditure relating directly to FAO's implementation of technical assistance projects. In this context, the World Health Organization (WHO) share of the Joint FAO/WHO Food Standards Programme (Codex Alimentarius) is part of extrabudgetary resources, but is not part of the field programme. Conversely, the TCP and the provision for the SPFS are funded from the Regular Programme but are included as part of the field programme.

33. The ratios of 2000-01 expenditure of the field programme and the Regular Programme funded programme of work for Chapter 2: Technical and Economic Programmes are shown in Table 2.4. Field programme expenditures were more than twice those of the programme of work. However, there were significant differences between the Major Programmes. Major Programme 2.1: Agricultural Production and Support Systems accounted for 70 percent of total field programme expenditures in 2000-01 and had the highest ratio, with field programme expenditure over five times that of the programme of work. It should be noted, however, that the ratio would fall to 2.5 if the effect of the Iraq Oil for Food Programme were excluded. Major Programme 2.4: Forestry, also had a relatively high ratio, with expenditure on the field programme 2.1 times that of the programme of work. On the other hand, expenditure on the field programme for Major Programme 2.2: Food and Agricultural Policy and Development was only about a third that of the programme of work. The ratio was also less than 1.0 for Major Programme 2.3: Fisheries.

Table 2.4. RATIO OF FIELD PROGRAMME AND PROGRAMME OF WORK EXPENDITURES UNDER CHAPTER 2:TECHNICAL AND ECONOMIC PROGRAMMES, 2000-01

Major Programme

Normative programme of work US$ '000

Field programme US$ '000

Ratio of field to programme of work

2.1 Agricultural Production and Support Systems

86,912

466,418

5.4

2.2: Food and Agriculture Policy and Development

83,389

37,110

0.4

2.3: Fisheries

38,113

29,685

0.8

2.4: Forestry

30,520

62,672

2.1

2.5: Contributions to Sustainable Development and Special Programme Thrusts*

38,935

68,016

1.7

Total

277,869

663,901

2.4

* To avoid distorting the ratio, the Regular Programme funded programme of work for Chapter 2 comprises all Regular Programme expenditure excluding SPFS project delivery, which amounted to US$9.3 million in 2000-01. SPFS delivery is included under the column headed Field programme.




1 FC 99/5, Financial Outturn of the 2000-01 Biennium

2 Expenditure of US$705.5 million against the final 2000-01 budget compares with US$669.8 million reported as General and Related Funds expenditure in the draft financial accounts (see Table 2.1). The former figure comprises only those items of expenditure in the financial accounts that are chargeable to the 2000-01 Programme of Work and Budget. Specifically:

Top Of PageTable Of ContentsNext Page