AQUACULTURE DEVELOPMENT AND COORDINATION PROGRAMME

- Guidelines for bioprogramming and design

Prepared by
Carol M. Brown (Consultant)
Colin E. Nash

UNITED NATIONS DEVELOPMENT PROGRAMME
FAO - FOOD AND AGRICULTURE ORGANIZATION OF THE UNITED NATIONS
Rome, 1988

The designations employed and the presentation of material in this publication do not imply the expression of any opinion whatsoever on the part of the Food and Agriculture Organization of the United Nations concerning the legal status of any country, territory, city or area or of its authorities, or concerning the delimitation of its frontiers or boundaries.

All rights reserved. No part of this publication may be reproduced, stored in a retrieval system or transmitted in any form or by any means, electronic, mechanical, photocopying or otherwise, without the prior permission of the copyright owner. Applications for such permission, with a statement of the purpose and extent of the reproduction, should be addressed to the Director, Publications Division, Food and Agriculture Organization of the United Nations, Via delle Terme di Caracalla, 00100 Rome, Italy.

FAO

This electronic document has been scanned using optical character recognition (OCR) software and careful manual recorrection. Even if the quality of digitalisation is high, the FAO declines all responsibility for any discrepancies that may exist between the present document and its original printed version.


Table of Contents


PREFACE

1. INTRODUCTION

2. PHASE I. BIOPROGRAMMING

2.1 Project goals and concepts
2.2 Biological design criteria
2.3 Facility characterization or programming

2.3.1 Programming approach
2.3.2 Programming infrastructure

2.4 Siting
2.5 Schematic design
2.6 Financial analysis
2.7 Environmental analysis
2.8 Conclusion

3. PHASE II. DESIGN

3.1 Preliminary design
3.2 Final design
3.3 Cost re-evaluation or value engineering
3.4 Construction documents and bid specifications

4. PHASE III. IMPLEMENTATION SERVICES

4.1 Bid assistance
4.2 Construction services
4.3 Technical assistance

5. SUMMARY

6. REFERENCES

APPENDIX I - Typical terms of reference for planning and design team

APPENDIX II - Project goals and concepts

APPENDIX III - Biological design criteria

APPENDIX IV - Programming infrastructure - The water system

APPENDIX V - Siting criteria