Previous Page Table of Contents Next Page


Appendix 5 - Description and cost breakdown of fuelwood plantation model and indigenous woodland management

A5.1 Fuelwood Plantation Model Description

A5.1.1 Site Selection

Establishment techniques and silvicultural treatments for this model are designed for the hardveld of eastern Botswana. The sites chosen should ideally be flat or gently sloping with well drained soils of a depth exceeding one metre. Shallow or stony soils should be avoided, as should pans and frost hollows. However, if small areas of these are unavoidable, they should be left unplanted and colonisation by indigenous species encouraged. Sites should, if possible, be within 8 km of the town or urban centre they are intended to supply.

A5.1.2 Species

From observation of the existing plantations in eastern Botswana, the most promising plantation species, in terms of survival and volume production, are Eucalyptus camaldulensis and Eucalyptus tereticornis. This is also borne out by the performance of these two species in other arid and semi-arid African countries. Recommended provenances of these two species are those from the Northern Territory and northern Queensland of Australia. This is in preference to material of southern Australian or South African origin.

Eucalyptus sider-oxylon was also seen to have potential as a plantation species, while E. grandis, although growing well in some restricted areas is not recommended as the rainfall is generally too low for this species and it has little frost resistance.

Several other species of Eucalyptus were observed, including E. maculata, E. maideni and E. paniculata, but none was comparable with E. camaldulensis and E. tereticornis in terms of production volume.

In addition to the Eucalypts, other species would appear to have potential as fuelwood producers and should be planted experimentally. These species are:

Acacia saligna
Albizia lebbek
Azadiracta indica
Casuarina cunninghamiana
Prosopis spp.

A5.1.3 Mean Annual Increment (MAI)

The mean annual increment (MAI) of any species is influenced by many factors. Apart from the obvious factors of site conditions and climate, the rotation length and stocking density of plantations have considerable effects. With the species of Eucalyptus proposed in the plantation model, the annual rate of growth rises to a peak after approximately 5 years and then falls off in arid areas; hence the longer the rotation length the lower the MAI. The rotation lengths proposed in the plantation model (see section 5.1.4) will ensure that the maximum mean annual increment will be achieved - 7 m3/ha/year should be expected from this model.

It should also be noted that the plantation model is for the production of fuelwood, thus some branchwood as well as the stem should be included in the estimation of MAI.

In arid areas throughout the world, mean annual increments of between 1 m3/ha and 20 m3/ha have been recorded for Eucalyptus camaldulensis. The figure of 7 m3/ha/year used in the plantation model is considered to be appropriate to the general conditions in Eastern Botswana and takes into account the factors mentioned above plus the proposed irrigation in the first year; it also assumes the intelligent selection of suitable planting sites (see Section A5.1.1).

A faster rate of growth can be expected from coppice regeneration after a harvest than from the initial seedling rotation, due to the existence of a well developed root system. However, this benefit is reduced due to the death of a proportion of root stocks every rotation and by a gradual decline in vigour with successive coppice rotations. Table A5.1 (a) indicates the effect this would have on the fuelwood plantation model.

A5.1.4 Rotation length

For Eucalyptus camaldulensis and E. tereticornis an initial seedling rotation of 6 years is recommended. Subsequently the coppice regeneration should be felled every 5 years. Replanting should take place after the fourth rotation.

Longer rotations than those recommended are not suitable for fuel-wood plantations, as stem diameter is then in excess of fuelwood requirements, and competition for soil moisture becomes a limiting factor.

A5.1.5 Fencing

It is essential that plantations should be protected from livestock for the first 3 years of the seedling rotation, and for the first 2 years of coppice rotations. Although temporary fencing or traditional thorn fencing could be used during these periods, the short rotations and annual harvesting (once the plantation has matured) proposed, suggests that a permanent perimeter fence would be more efficient. The fencing proposed in these models is of veldspan netting with one top and one bottom strand of barbed wire. When fencing a plantation, fence posts and droppers should be used between straining posts. Further specifications of the proposed fences are included in the first year costs of the model.

A5.1.6 Site preparation

The chosen site should be cleared by hand of all woody vegetation. Initially, all trees and shrubs should be felled, except those occurring on areas unsuitable for planting, and the resulting wood crosscut and stacked for subsequent sale of fuelwood. All stumps should then be uprooted and piled for burning when sufficiently dry. Termite mounds should be broken open and liberally soaked with an 0.5% solution of a suitable insecticide (e.g. 'Shelldrite').

TABLE A5.1 (a) - Wood Volume per Surviving Root Stock, Labour and Tool Requirements for each Year of Harvesting (500 ha Plantation Model)

Year of Harvesting

Surviving Root Stocks per ha

MAI (m3/ha/yr)

Volume per root stock (m3)

No. of Stumps Harvested per man days

Man days per ha

Labour Force required for 100 ha

Tool Cost per ha (P)

7

1,200

7

0.0350

24

50

50

P 6.85

12

1,080

7.70

0.0356

23

47

47

P 6.44

17

972

6.55

0.0337

25

39

39

P 5.35

22

875

5.24

0.0299

28

31

31

P 4.22

The labour requirement for site clearing will depend on the density of existing vegetation. For the purpose of this model, it is assumed that the vegetation consists of open savanna woodland or scrub regrowth on abandoned farmland requiring a labour input of 70 man days/ha to clear.

A5.1.7 Roads and rides

For the 500 ha model, the suggested networks of roads and rides have been laid out (see Figure A5.1 a) in such a way that, during harvesting, the maximum distance which wood will have to be carried to a roadside, or to the external fire trace, is 100 m. Roads should be 10 m wide and levelled, either by tractor mounted grader or by hand, to facilitate access by tractor, small lorries and pick-ups.

Unplanted rides should be 7.5 m wide and may be left unlevelled, as their function is to act as fire breaks. The 50 ha model network is also shown (Figure A5.1 (b)).

A5.1.8 Pre-planting cultivation

Complete disc ploughing should be undertaken after the first rains to encourage maximum absorption of rainfall and to reduce weed cover. On gently sloping sites, ploughing should be parallel to the ground contours and, if available, a reversible plough should be used so that soil is always turned up the slope.

Ploughing should be followed by a sub-soiling to a depth of 60 cm, using a single tyne sub-soiler, along planting lines to shatter compacted soil. This will have the double effect of marking planting lines and of encouraging rapid downward root development.

Sub-soiling is considered to be essential for good survival and growth of plantations or woodlots; thus if it is not possible to undertake both ploughing and sub-soil operations, it is recommended that sub-soiling be given precedence.

Ploughs are manufactured in the UK and other countries which can combine the surface cultivation and the sub-soiling in a single operation. The savings which could be achieved by using them would justify a special purchase.

A5.1.9 Planting operations

The recommended stocking density for fuelwood plantations is 1,333 stems/ha planted at a spacing of 3.0 m x 2.5 m.

Polypot seedlings are recommended, each pot containing approximately one liter of soil. The use of "Chibuku" cartons in place of polypots is quite acceptable if drainage holes are provided. Seedlings should be well formed, vigorous and approximately 30 cm in height. Malformed or overgrown seedlings should be rejected. About one week before planting, the seedlings should be soaked with a 0.2% solution of a suitable insecticide (e.g. 'Shelldrite') as protection against termites.

Figure A5.1 (a) Eastern Botswana: 500 ha Plantation Model Suggested Road Network for Level Site of ha (1) (Scale 1:5000)

(1) Plantation to be built up using five such, 100 ha sites.

Figure A5.1 (b) EASTERN BOTSWANA: 50 ha COMMUNITY WOODLOT MODEL SHOWING SUGGESTED ROAD NETWORK

Planting should normally be undertaken in December but timing will depend on rainfall. At least one good rain (>25 mm) would be necessary before planting.

Each seedling should be planted in the centre of an 80 cm diameter 'dish' which should be slightly lower than ground level to retain water in the vicinity of each seedling. The polypot or carton should first be removed from the root ball and the seedling then planted so that the root collar is level with the soil surface of the 'dish'.

A5.1.10 Watering

Each seedling should be watered immediately after planting and thereafter every three weeks in the absence of rain, until the end of May. Watering may also be required during the growing season in the year after planting.

For fuelwood plantations, a tractor towed 5,000 litre bowser may be used to carry water along planted rows and from this water can be delivered into each 'dish' using a flexible hose. By attaching a 'T' junction to the bowser outlet, two hoses can be used enabling two rows of trees to be watered simultaneously. A valve situated at the delivery end of each hose and operated by the labourer responsible for watering would prevent wastage of water when moving from tree to tree. Ten litres of water should be delivered to each tree at each watering.

A5.1.11 Fertiliser

Boronated superphosphate and 2:3:2 fertilisers should be applied as a top dressing at the rate of 50 kg/ha each. At least two weeks should elapse between planting and fertiliser application. For large scale plantations, the fertilisers may be applied by a fertiliser spreader, while for community woodlots the fertilisers should be applied by hand around each tree, taking care to avoid direct contact.

A5.1.12 Weeding

For large scale plantations inter-row disc harrowing followed by manual line weeding should be undertaken twice in the year of planting, twice in the following year and one disc harrowing in the third year. The timing of these operations will largely be dictated by weed growth, but the second weeding should leave the plantation clean at the end of the rainy season so that available soil moisture is retained for the benefit of the tree crop. Any damage to planting 'dishes' caused by harrowing should be repaired during manual line weeding and the dishes mulched with the weeds as they are removed.

Because of the narrower inter-row spacing suggested for community woodlots and because it is desirable to minimise mechanical operations, clear weeding by hand is recommended. The frequency of weedings will be the same as for large scale plantations.

A5.1.15 Beating-up (blanking)

This operation should be undertaken two months after planting if seedling mortality within the plantation or woodlot exceeds 10%. 15% is assumed for the first year and 10% overall during the first rotation. It is possible for beating-up to be delayed until the start of the following year but this is not ideal in view of the short rotations proposed here.

If localised high mortality occurs, the cause should be identified before beating-up or replanting is considered as this may be due to adverse local site factors (e.g. shallow soil), in which case beating-up is pointless.

The same size of seedling as used in the original planting should be used for beating-up. Overgrown seedlings should not be used.

A5.1.14 Termite control

All termite mounds should have been destroyed during the site clearing operation. Plantations should be periodically checked for termite attack and any damage treated at once by applying 2.5 l of 0.2% 'Shelldrite' solution to every tree in and around the area (s) of damage. For the purpose of this model it is assumed that one application of 'Shelldrite' solution will be required while a contingency figure is included in the annual costs in case of further attacks.

A5.1.15 Fire protection

An external fire trace at least five metres wide should be maintained around each plantation. In addition, road margins and rides should be kept clean to act as internal fire breaks. Fire traces and fire breaks may be cleared annually or by disc harrowing.

A5.1.16 Harvesting

Plantations will he harvested initially after six growing seasons, and thereafter coppiced on a 5-year rotation. They will be clear felled using bow saws and the produce cross-cut to length, carried and stacked at the roadside. (The felling cuts should be angled to promote water runoff and the resulting stumps should be no more than 10 cm high.) For labour requirements etc., see Table A5.1 (b). For community woodlots, wood should be sold standing, with the buyer responsible for felling, which will be under supervision.

A5.1.17 Replanting

After four rotations (1 seedling and 3 coppice), it will be necessary to replant due to stump mortality loss of vigour in surviving root-stocks. Replacement seedlings should be planted between existing stumps. With the exception of site cultivation and mechanical weeding, all operations will be the same as detailed for initial planting.

Table A5.1 (b) Direct Costs Summary: 500 ha Plantation Model

year

labour

tractor

materials

seedlings

total

foreign

for ex %

1

57678.57

74890.82

20341.63

35844.12

188755

113706.84

62.89

2

70009.19

56383.92

11777.7

35844.12

174015

91657.25

52.67

3

73292.85

58016.36

12387.7

35844.12

179541

93226.96

51.93

4

73028.88

31567.86

12997.7

35844.12

153439

67040.01

43.69

5

73967.74

32108.33

13607.7

35844.12

155528

67845.34

43.62

6

19062.25

39177.12

5501.3


63741

39374.89

61.77

7

25584.45

3794.32

4431.3


33810

5757.93

17.03

a

22849.44

2757.5

4431.3


30038

5032.16

16.75

9

22849.44

2757.5

4431.3


30038

5032.16

16.75

10

22849.44

2757.5

4431.3


30038

5032.16

16.75

11

22849.44

29757.5

4431.3


57038

32032.16

56.16

12

21410.65

2757.5

4383.3


28551

4998.56

17.51

13

21410,65

2757.5

4383.3


28551

4998.56

17.51

14

21410.65

2757.5

4383.3


28551

4998.56

17.51

15

21410.65

2757.5

4383.3


28551

4998.56

17.51

16

21410.65

29757.5

4383.3


55551

31998.56

57.60

17

18220.48

2757.5

4255.3


25233

4908.96

19.45

18

18220.48

2757.5

4255.3


25233

4908.96

19.45

19

18220.48

2757.5

4255.3


25233

4908.96

19.45

20

18220.48

2757.5

4255.3


25233

4908.96

19.45

21

18220.48

29757.5

4255.3


52233

31908.96

61.09

22

36614.02

39695.53

8803.2

35844.12

120957

77893.23

64.40

Financial Costs

718791.36

455239.26

150766.43

215064.72

1539862

712168.70

46.25

Economic Shadow Price Factor

0.5

1.1 (1)

1.1 (2)

1.1

(1) Estimated as 100% of tractor costs, 65% of tractor running and material costs
(2) In fact, the foreign element of these costs varies from 65-95% but no adjustment has been to the 1.1 shadow price factor since the change is well within the limits of accuracy anyway.

A5.1.18 Protection

Large-scale plantations will require protection against fire, livestock, unauthorised felling and other hazards. Locally recruited forest guards should be employed (at a salary equivalent to the government minimum wage), each protecting 200 ha.

A5.1.19 Supervision

Plantations will require a level of supervisory input necessary to utilise the services of technical assistants (Forestry Diplomates). Each 100 ha block will require 7 man-months of supervision during the year of establishment and 2, 1 and 0.5 man-months for maintenance operations in years 2, 3 and 4 respectively. Harvesting will require 3 man-months supervision and replanting a further 4 man-months. In addition, there will be an annual requirement of 5 man-days of supervision of each block to ensure adequate protection against the previously detailed hazards.

Experience in Botswana has shown that each major 500 ha plantation requires full-time supervision if it is to develop successfully. After 8-10 years the level of supervision can be reduced to 2-3 man-months, except in harvesting years. It is possible that as second 500 ha units are added in the same area, these can also be supervised by the same technical assistants.

The present salary of a Forest Supervisor is in the region of P4,500 per annum. In addition, each supervisor will require a motor cycle costing approximately P3,000. Supervisors will be entitled to suitable accommodation for which a maintenance cost of P900 per annum is included in Table A5.1 (c). An office and store will be required for each 500 ha of plantation and annual maintenance costs of P900 are also included.

A5.1.20 Management

It is assumed that management will be the responsibility of a professional Forest Officer through a District Office. The salaries of the Forest Officer and his supporting staff are estimated as follows:

1 Forest Officer

P 6,500 per year

1 Accounts Clerk

P 3,500 per year

1 Clerk/Typist

P 4,500 per year

1 Driver

P 2,150 per year


P 16,650 per year

In addition, one 4x4 vehicle will be required, for which the annual costs are estimated at P7,380. Maintenance of office buildings is further estimated at P2,500 per year.

It is assumed that a Forest Officer will be able to manage four such plantations as outlined in these models. Thus, the costs used in Table A5.1 (c) are a quarter of those shown above.

Table A5.1 (c). INDIRECT COSTS, DIRECT COSTS AND YIELDS: 500 ha PLANTATION MODEL

Year

protection wages

supervision

management

direct costs

total costs

foreign costs

% foreign exchange (1)

yield (m3)

salaries

vehicles

buildings

salaries

vehicles

buildings

1

1916

5750

1807

1142

4163

1845

625

188755

206003

121991

59.22

2500

2

1916

5750

2364

1309

4163

1845

625

174015

191987

95445

49.71

2500

3

3832

5750

2670

1401

4163

1845

625

179541

199827

97290

48.69

2500

4

3832

5750

2852

1456

4163

1845

625

153439

173962

71267

40.97

2500

5

3832

5750

2909

1473

4163

1845

625

155528

176125

72124

40.95

2500

6

3832

5750

1159

948

4163

1845

625

63741

82063

42078

51.28

-

7

3832

5750

1409

1023

4163

1845

625

33810

52457

8687

16.56

3926

8

3832

5750

1159

948

4163

1845

625

30038

48360

7736

16.00

3926

9

3832

1723

1034

910

4163

1845

625

30038

44170

7623

17.26

3926

10

3832

1723

1034

910

4163

1845

625

30038

44170

7623

17.26

3926

11

3832

1723

1034

910

4163

1845

625

57038

71170

34623

48.65

3926

12

3832

5750

1034

910

4163

1845

625

28551

46710

7590

16.25

3601

13

3832

1723

1034

910

4163

1845

625

28551

42683

7590

17.78

3601

14

3832

1723

1034

910

4163

1845

625

28551

42683

7590

17.78

3601

15

3832

1723

1034

910

4163

1845

625

28551

42683

7590

17.78

3601

16

3832

1723

1034

910

4163

1845

625

55551

69683

34590

49.64

3601

17

3832

5750

1034

910

4163

1845

625

25233

43392

7500

17.28

3063

18

3832

1723

1034

910

4163

1845

625

25233

39365

7500

19.05

3063

19

3832

1723

1034

910

4163

1845

625

25233

39365

7500

19.05

3063

20

3832

1723

1034

910

4163

1845

625

25233

39365

7500

19.05

3063

21

3832

1723

1034

910

4163

1845

625

52233

66365

34500

51.99

3063

22

3832

5750

2034

1210

4163

1845

625

120957

140416

81384

57.96

2450

Financial Costs

80472

82203

31805

22740

91586

40590

13750

1539862

1903008

777324

40.85

67900

Economic Shadow Price Factor

0.5

1.6

1.1

1.6

1.1

(1) Combining foreign figure for direct costs with foreign exchange element in indirect costs (estimated as 90% of vehicle costs).

A5.2 500 ha Fuelwood Plantation Model - Resource Requirements and Costs

In this section we describe the detailed resource requirements, output and costs for a large (500 ha) plantation. The yield from such a plantation would, by year 7, approximately meet the needs of a town/major village of 7,000-10,000.

Species:

Eucalyptus camaldulensis - N Australian provenance
Eucalyptus tereticornis - N Australian provenance
Eucalyptus sider-oxylon

Rotation Lengths:

1st rotation 6 years, followed by three coppice rotations of 5 years.

Stocking Density:

1,333 stems/ha at 3.0 x 2.5 m spacing

MAI:

7 m3/ha/yr

Year 1

a) Preliminary works

Fencing of 500 ha site: veldspan netting with 1 top and 1 bottom strand of barbed wire. Creosoted straining post every 100 m and at every angle plus creosoted fence posts every 10 m and droppers every 2.5 m. Two gates 3.6 m wide of tubular metal. Total length 9,000 m.

Materials:

(Pula)


2 rolls binding wire at P 7.50

15.00


90 rolls veldspan 10-47 at P 69.00

6,210.00


36 rolls barbed wire at P 47.00

1,692.00


60 kg staples at P 1.50

90.00


92 No. straining posts 3 m x 100 m creosoted at P 5.00

460.00


810 No. creosoted fence posts 1.8 m x 75 mm at P 2.40

1,944.00


2,430 No. creosoted droppers at P 0.50

1,215.00

Transport: 1 tractor hour per 700 m at P 11.03/hr

141.50

Labour: 6 man days per 100 m at P 4.50/man day

2,430.00

Total

14,198.00

b) Establishment: Compartment I (100 ha total area, 93.53 ha planted)


(Pula)

Site clearing (100 ha): felling, uprooting, cross-cutting, stacking, destructions of termite mounds.



Assuming site is scrub regrowth or open savanna: 70 man day/ha

31,500.00


Insecticide (0.5% solution) 2 litres/ha at P 5.00/litre

1,000.00

Ground cultivation (93.53 ha) complete disc ploughing at 4 tractor hours/ha at P 11.03

4,126.54


Subsoiling to depth of 60 cm along planting lines 3.0 m apart: 2 tractor hrs/ha

2,063.27

Pre-planting: preparation of circular planting dish 80 cm in diameter, slightly below ground level at 8 man days/ha

3,367.08

Planting: 3.00 x 2.5 m spacing = 1,333 stems/ha



Seedings at 25 thebe each*

31,168.87


Transport: 2 tractor hrs/ha

2,063.27


Labour: 150 seedlings/man days

3,740.26

Fertiliser: 50 kg/ha of 2:3:3 plus 50 kg/ha of boronated superphosphate at P 15/50-kg bag

2,805.90


Tractor houses: 1/ha

1,033.64

Beating-up (Blanking): January-February



Assuming 15% mortality:



Seedlings: 13,701 at 25 thebe each*

4,675.25


Transport: 0.5 tractor hrs/ha

515.80


Labour: 130 seedlings/man day

647.35

Road construction: 3,620 m of 10 m wide road levelled by tractor-mounted grader at 1,000 m2/tractor hour 1,000 m of unplanted ride

399.29

Total

89,104.00

* Cost of seedlings is broken down into: Labour 20 thebe each, Materials 5 thebe each.

c) Maintenance: Compartment I


(Pula)

Watering: 10 litres per tree immediately after planting and thereafter 10 litres every 3 weeks, in the absence of rain until May. Water distribution by tractor towed bowser.



Av. 30 l/tree



Water: 3,740 m3 at P 0.50/m3

1,870.00


Transport: 2 tractor hrs/ha x 3

6,321.66


Labour: 6 man days/ha x 3

7,576.16

Weeding:



2 line weedings by hand, including repair and mulching of planting dishes at 8 man days/ha x 2

6,734.16


2 mechanical inter-row weedings at 1 tractor hr/ha x 2

2,063.27

Termite control: as a contingency against termite attack it is assumed that one application of 2.5 litres/tree of 0.2% Shelldrite solution will be required:



Insecticide: 6.5 litres/ha at P 5.00/litre

3,039.73


Transport: 2 tractor hrs/ha

2,063.27


Labour: 4 man days/ha

1,683.54

Fire tracing:



disc harrowing of 5 m wide external trace: 2.1 ha at 2 tractor hrs/ha

46.33


Harrowing of road margins and rides: 2.56 ha at 2 tractor hrs/ha

56.47

Total

31,454.00

Tractor purchase: 2 tractors at P 27,000 each

54,000.00

Total for Year 1

P 188,755.00

Year 2


(Pula)

Establishment: Compartment II

89,104.00

Maintenance:


Watering: Compartments I and II (187.06 ha):



Average 30 litres water per tree:



Water: 7,481 m3 at P 0.50/m3

3,740.50


Transport: 2 tractor hrs/ha x 3

12,379.63


Labour: 6 man days/ha x 3

15,151.86

Weeding: Compartments I and II:



2 line weedings by hand, including repair and mulching of planting dishes at 8 man days/ha x 2

13,468.32


2 mechnical inter-row weedings at 1 tractor hr/ha x 2

4,126.54

Termite control: Compartment II:



1 application of 0.2% Shelldrite solution at 2.5 litre/tree



Compartment I: contingency allowance at 20% of Year 1 costs



Insecticide: 730 litres at P 5.00/litre

3,650.00


Transport: 224 tractor hours

2,466.91


Labour: 450 man days

2,024.64

Fence maintenance: contingency at 5% Year 1 costs



Materials

581.30


Transport

7.08


Labour

121.48

Road maintenance: 3,620 m of roads: contingency at 10% of Year 1 costs



Tractor hours

39.87

Fire tracing: disc harrowing of 5 m wide external trace:



4.2 ha at 2 tractor hrs/ha

92.51


Harrowing of road margins and rides 5.12 ha at 2 tractor hours/ha

112.77

Total

147,015.00

Tractor Purchase: 1 tractor at P 27,000

27,000.00

Total: Year 2

174,015.00

Year 3


(Pula)

Establishment: Compartment III

89,104.00

Maintenance:


Watering: Compartments II and III



Average 3 applications at 10 litres/tree



Water: 7,481 m3 x P 0.50/m3

3,740.50


Transport: 2 tractor hrs/ha x 3

12,379.63


Labour: 6 man days/ha x 3

15,151.86

Weeding:



Compartment I:




1 line weeding by hand at 7 man days/ha

2,946.20



1 mechanical inter-row weeding at 1 tractor hr/ha

1,031.64


Compartments II and III:




2 line weedings by hand, including repair and mulching of dishes at 8 man days/ha x 2

13,468.32



2 mechanical inter-row weedings at 1 tractor hr/ha x 2

4,126.54

Termite control:



Compartment III:




1 application of 0.2% Shelldrite solution at 2.5 litre/tree



Compartments I and II:




Contingency at 20% of Year 1 costs




Insecticide: 852 litres at P 5.00/litre

4,260.00



Transport: 251 tractor hrs

2,879.09



Labour: 525 man days

2,362.11

Fence maintenance: 5% contingency



Materials

58.30


Transport

7.06


Labour

121.48

Road maintenance: 7,240 m of roads at 10% contingency cost:



Tractor hours

79.86

Fire tracing: Disc harrowing of 5 m wide external trace plus road margins and rides:



13.98 ha at 2 tractor hrs/ha

308.43

Total

152,541.00

Tractor Purchase: 1 tractor at P 27,000

27,000.00

Total: Year 3

179,541.00

Year 4


(Pula)

Establishment: Compartment IV

89,104.00

Maintenance


Watering: Compartments III and IV:



average of 3 applications at 10 litres/tree



Water: 7,481 m3 at P 0.50/m3

3,740.50


Transport: 2 tractor hrs/ha x 3

12,579.63


Labour: 6 man days/ha x 5

15,151.86

Weeding:



Compartment II:




1 line weeding by hand at 7 man days/ha

2,946.20



1 mechanical inter-row weeding at 1 tractor hr/ha

1,031.64


Compartments III and IV:




2 line weedings by hand including repair and mulching of dishes at 8 man days/ha x 2

13,468.32



2 mechanical inter-row weedings at 1 tractor hr/ha x 2

4,126.54

Termite control:



Compartment IV:




1 application of 0.2% Shelldrite solution at 2.5 litres/tree



Compartments I, II and III:




contingency at 20% of Year 1 costs




Insecticide: 974 litres at P 5.00/litre

4,870.00



Transport; 298 tractor hrs

3,286.94



Labour: 600 man days

2,700.00

Fence maintenance: 5% contingency costs



Materials

581.50


Transport

7.08


Labour

121.48

Road maintenance: 10,860 m of roads at 10% contingency cost



Tractor hours

119.80

Fire tracing: Disc harrowing of 5 m wide external trace plus road margins and rides:



18.64 ha at 2 tractor hr/ha

411.20

Total: Year 4

153,439.00

Year 5


(Pula)

Establishment: Compartment I

89,104.00

Maintenance


Watering: Compartments VI and V:



average of 5 applications at 10 litres/tree



Water: 7,481 m3 at P 0.50/m3

3,740.50


Transport: 2 tractor hrs/ha x 3

12,379.63


Labour: 6 man days/ha x 3

15,151.86

Weeding:



Compartment III:




1 line weeding by hand at 7 man days/ha

2,946.20



1 mechanical inter-row weeding at 1 tractor hr/ha

1,031.64


Compartments IV and V:




2 line weedings by hand including repair and mulching of dishes at 8 man days/ha x 2

13,468.32



2 mechanical inter-row weedings at 1 tractor hr/ha x 2

4,126.54

Termite control:



Compartment V:




1 application of 0.2% Shelldrite solution at 2.5 litres/tree



Compartments I-IV:




contingency at 20% of Year 1 costs




Insecticide: 1,096 litres at P 5.00/litre

5,480.00



Transport: 335 tractor hrs

3,695.05



Labour: 675 man days

3,037.50

Fence maintenance: 5% contingency costs



Materials

581.30


Transport

7.08


Labour

121.48

Road maintenance: 14,480 m of roads at 10% contingency cost



Tractor hours

159.71

Fire tracting: Disc harrowing of 5 m wide external trace plus road margins and rides:



23.3 ha at 2 tractor hr/ha

514.00

Total: Year 5

155,528.00

Year 6


(Pula)

Maintenance


Watering: Compartment V:



average of 5 applications at 10 litres/tree



Water: 3,740 m3 at P 0.50/m3

1,870.00


Transport: 2 tractor hrs/ha x 3

6,322.18


Labour: 6 man days/ha x 3

7,576.18

Weeding:



Compartment IV:




1 line weeding by hand at 7 man days/ha

2,946.20



1 mechanical inter-row weeding at 1 tractor hr/ha

1,031.64


Compartment V:




2 line weedings by hand including repair and mulching of dishes at 8 man days/ha x 2

6,733.04



2 mechanical inter-row weedings at 1 tractor hr/ha x 2

2,063.27

Termite control: Compartments I to V:



contingency at 20% of Year 1 costs



Insecticide: 610 litres at P 5.00/iitre

3,050.00


Transport: 185 tractor hrs

2,040.55


Labour: 375 man days

1,687.22

Fence maintenance: 5% contingency costs



Materials

581.30


Transport

7.08


Labour

121.48

Road maintenance: 18,100 m of roads at 10% contingency cost



Tractor hours

199.64

Fire tracting: Disc harrowing of 5 m wide external trace plus road margins and rides:



23.3 ha at 2 tractor hr/ha

514.00

Total

36,741.00

Tractor Purchase: 1 tractor at P 27,000

27,000.00

Total: Year 6

63,741.00

Year 7


(Pula)

Harvesting: Compartment I



Estimated MAI = 7 m3/ha/yr.*
Assuming 1,200 stems/ha* survive, each will have a volume of 0.035 m3*
24 trees/man days* felled, crosscut and stacked at roadside = 50 man days/ha*

21,040.75


To complete all felling in 3 months, 50 labourers* required, each with 1 bowsaw spare blades and 1 machete: cost per unit = P 16.00

800.00

Maintenance


Weeding: Compartment V:



1 line weeding by hand at 7 man days/ha

2,945.71


1 mechanical inter-row weeding at 1 tractor hr/ha

1,031.64

Termite control: Compartments I to V:



contingency at 20% of Year 1 costs



Insecticide: 610 litres at P 5.00/litre

3,050.00


Transport: 185 tractor hrs

2,040.55


Labour: 375 man days

1,687.22

Fence maintenance: 5% contingency costs



Materials

581.30


Transport

7.08


Labour

121.48

Road maintenance: 18,100 m of roads at 10% contingency cost



Tractor hours

199.64

Fire tracting: Disc harrowing of 5 m wide external trace plus road margins and rides:



23.3 ha at 2 tractor hr/ha

514.00

Total: Year 7

35,810.00

* See Table A5.1 (a) for appropriate figures for harvesting from Years 12, 17 and 22.

Years 8 to 11


(Pula)

Harvesting: One compartment should be felled each year. Coppice regeneration should be harvested on a 5-year rotation. For years 8 to 11, costs will be the same as for Year 7. For subsequent years the costs will vary with the labour requirements as shown in Table 1.2



Labour: 50 man days/ha

21,040.75


Tools:

800.00

Maintenance


Termite control: contingency at 20% of Year 1 costs



Insecticide: 610 litres at P 5.00/litre

3,050.00


Transport: 185 tractor hrs

2,040.55


Labour: 375 man days

1,687.22

Fence maintenance: 5% contingency costs



Materials

581.30


Transport

7.08


Labour

121.48

Road maintenance: 18,100 m of roads at 10% contingency cost



Tractor hours

199.64

Fire tracting: Disc harrowing of 5 m wide external trace plus road margins and rides:



23.3 ha at 2 tractor hr/ha

514.00

Total: Years 8-10

3,038.00

Tractor Purchase: 1 tractor at P 27,000 in Year 11

27,000.00

Total: Year 11

30,038.00

Years 12-16


(Pula)

Harvesting: One compartment should be felled each year.



Estimated MAI = 7.7 m3/ha/yr.* Assuming 1,080* root stocks per hectare have survived, each will carry a volume of 0.0356 m3.* 23 root stocks/man day* felled, crosscut and stacked at roadside = 47 man days/ha.*

19,778.30


To complete the felling in 3 months, 47 labourers will be required, each with 1 bowsaw, spare blades and 1 machete, at a cost of P 16.00 per unit

752.00

Maintenance:


Termite control: Whole plantation:



contingency at 20% of Year 1 costs



Insecticide: 610 litres at P 5.00/litre

3,050.00


Transport: 185 tractor hrs

2,040.55


Labour: 375 man days

1,687.22

Fence maintenance: 5% contingency costs



Materials

581.30


Transport

7.08


Labour

121.48

Road maintenance: 18,100 m of roads at 10% contingency cost



Tractor hours

199.64

Fire tracting: Disc harrowing of 5 m wide external trace plus road margins and rides:



23.3 ha at 2 tractor hr/ha

514.00

Total: Years 12-15

28,551.00

Tractor Purchase: 1 tractor at P 27,000 in Year 16

27,000.00

Total: Year 16

55,551.00

* See Table A5.1 (a) for appropriate figures for harvesting from Years 7, 12, 17 and 22.

Years 17 to 21


(Pula)

Harvesting: One compartment should be felled each year.



Estimated MAI = 6.55 m/ha/yr* Assuming 972 root stocks/ha* have survived, each will carry a volume of 0.0337 m3.* 25 root stocks/man days* felled, crosscut and stacked at roadside = 30 man days/ha*

16,411.78


To complete the felling in 3 months, 39 labourers* will be required, each with 1 bowsaw, spare blades and 1 machete, at a unit cost of P 16.00

624.00

Maintenance:


Termite control: Whole plantation:



contingency at 20% of Year 1 costs



Insecticide: 610 litres at P 5.00/litre

3,050.00


Transport: 185 tractor hrs

2,040.55


Labour: 375 man days

1,687.22

Fence maintenance: 5% contingency costs



Materials

581.30


Transport

7.08


Labour

121.48

Road maintenance: 18,100 m of roads at 10% contingency cost



Tractor hours

199.64

Fire tracting: Disc harrowing of 5 m wide external trace plus road margins and rides:



23.3 ha at 2 tractor hr/ha

514.00

Total: Years 17-20

25,233.00

Tractor Purchase: 1 tractor at P 27,000 in Year 21

27,000.00

Total: Year 21

52,233.00

* See Table A5.1 (a) for appropriate figures for harvesting from Years 7, 12, 17 and 22.

Year 22


(Pula)

Harvesting: One compartment should be felled each year.



Estimated MAI = 5.24 m/ha/yr*
Assuming 875 root stocks/ha* have survived, each will carry a volume of 0.0299 m3.*
28 root stocks/man days* felled, crosscut and stacked at roadside = 31 man days/ha*
To complete the felling in 5 months, 31 labourers* will be required, each with 1 bowsaw, spare blades and 1 machete, at a unit cost of P 16.00

13,045.26

Replanting:


Pre-planting: preparation of planting dishes 80 cm in diameter between rows of stumps:



8 man days/ha

3,366.52

Planting: 1,335 seedlings/ha



Seedlings at 25 thebe each

31,368.87


Transport: 2 tractor hours/ha

2,028.67


Labour: 150 seedlings/man day

3,739.64

Fertiliser: 50 kg/ha of 2:3:2 plus 50 kg/ha of boronated superphosphate at P 15/50 kg bag

2,805.90


Transport: 1 tractor hour/ha

1,014.33

Beating-up (Blanking): undertaken in January-February



Assuming 15% mortality:




Seedlings: 18,701 at 25 thebe each

4,675.25



Transport: 0.5 tractor hrs/ha

515.82



Labour: 130 seedlings/man day

647.24

Maintenance


Watering: 10 litres/tree immediately after planting and thereafter 10 litres/tree every 3 weeks in the absence of rain, until May. Average of 3 applications



Water: 3,740 m34 at P 0.50/m3

1,870.00


Transport: 2 tractor hrs/ha x 3

6,322½18


Labour: 6 man days/ha x 3

7,574.92

Weeding: 2 line weedings by hand including repair and mulching of dishes at 8 man days/ha x 2

6,733.04

Termite control: Whole plantation: contingency at 20% of Year 1 costs



Insecticide: 610 litres at P 5.00/litre

3,050.00


Transport: 185 tractor hrs

2,040.55


Labour: 373 man days

1,687.22

Fence maintenance: 5% contingency costs



Materials

581.30


Transport

7.08


Labour

121.48

Road maintenance: 18,100 m of roads at 10% contingency cost



Tractor hours

199.64

Fire tracting: Disc harrowing of 5 m wide external trace plus road margins and rides:



23.3 ha at 2 tractor hr/ha

514.00

Total

93,957.00

Tractor Purchase: 1 tractor at P 27,000

27,000.00

Total: Year 22

120,957.00

* See Table A5.1 (a) for appropriate figures for harvesting from Years 7, 12, 17 and 22.

Yield (m3) from a 500 ha Fuelwood Plantation

Year

Compartment

Cumulative


I

II

III

IV

V

TOTAL

1

*2500





2500

2


*2500




5000

3



*2500



7500

4




*2500


10000

5





*2500

12500

6






12500

7

3928





16428

8


3928




20356

9



3928



24284

10




3928


28212

11





3928

32140

12

3601





35741

13


3601




39342

14



3601



42943

15




3601


46544

16





3601

50145

17

3063





53208

18


3063




56271

19



3063



59334

20




3063


62397

21





3063

65460

22

2450





67910

*Obtained from clearing of the indigenous woodland

Tractor Requirements: 500 ha Plantation Model

Year of Operation

Tractor Hours Required

Tractor Purchasing Requirements

Capital Cost (P.)

Annual Running Cost (Pula)*

1

1,894

2

54,000

20,890.82

2

2,664

1

27,000

29,383.92

3

2,812

1

27,000

31,016.36

4

2,862



31,567.86

5

2,911



32,108.33

6

1,104

1

27,000

12,177.12

7

344



3,794.32

8

250



2,757.50

9

250



2,757.50

10

250



2,757.50

11

250

1

27,000

2,757.50

12

250



2,757.50

15

250



2,757.50

14

250



2,757.50

15

250



2,757.50

16

250

1

27,000

2,757.50

17

250



2,757.50

18

250



2,757.50

19

250



2,757.50

20

250



2,757.50

21

250

1

27,000

2,757.50

22

1,151

1

27,000

12,695.53

Totals

19,242

9

243,000

212,239.30

*Annual running costs have been calculated at the rate of P 11.03 per vehicle hour.

This comprises the costs of fuel, lubricants, repairs and operator's wages, but excludes vehicle depreciation.

A5.3 50 ha Community Woodlot Model-Resource Requirements and Costs

PLANTED OVER 5 YEARS

Species:

Eucalyptus camaldulensis
Eucalyptus tereticornis
Eucalyptus sider-oxylon

Rotation length: 5 years - replanting after 4 rotations.

Year 1

a) Preliminary Works:

Fencing of 50 ha site: veldspan netting with 1 top and 1 bottom strand of barbed wire. Creosoted straining posts every 100 m with bush poles (bases soaked in sump oil) every 3 m. 1 gate 3.6 m tubular metal. Total length 2850 m.

Materials:

29 rolls veldspan 10-47 @ P69.00

2,001.00

12 rolls Barbed wire @ P47.00

564.00

20 Kg Staples @ P1. 50

30.00

30 No. Straining posts 3 m x 100 mm creosoted @ P5.00

150.00

880 No. Bush Poles @ P0.50

440.00

1 No. Gate: 3.6 m Tubuler metal @ P85.00

85.00


3,270.00

Transport: 1 tractor hour @ P18.00 per 700 m

73.29

Labour: 6 man days/100 m

897.75


P4,241.04

b) Establishment: Compartment I (10 ha total area, 9.36 ha planted)

Site Clearing (10 ha): felling, uprooting, crosscutting.



Stacking, destruction of termite mounds: Assuming site is scrub regrowth or open savanna: 70 man days/ha

3,675.00


Insecticide (0.5% solution) 2 litres/ha @ P5.00/litre

100.00

Ground Cultivation (9.68 ha):



complete disc ploughing @ 4 tractor hrs/ha @ hired rate of P18/hr.

696.96


Subsoiling to depth of 60 cm along planting lines 2.5 m apart @ 2.5 tractor hrs/ha

435.60

Pre-planting (9.36 ha): preparation of circular planting dish 80 cm wide, slightly below ground level, @ 9.5 man days/ha

466.83

Planting (9.36 ha): at 2.5 m x 2.5 m spacing = 1600 stems/ha



Seedlings @ 25 t each*

3,744.00


Transport: 2.5 tractor hrs/ha

421.20


Labour @ 150 seedlings/man day

524.16

Fertilizer: 50 kg/ha of 2:3:2 plus 50 kg/ha of boronated superphosphate applied as top dressing by hand.



100 Kg/ha fertilizer @ P15/50 Kg bag

300.00


Labour 5 man days/ha

245.70

Beating-up (Blanking): Jan.-February. Assuming 15% mortality:



Seedlings: 2247 @ 25t each*

561.75


Transport: 0.5 tractor hrs/ha

84.24


Labour: 1.6 man days/ha

78.62

Road Construction: 642 m of 10 m wide road levelled by hand at 1 man day/250 m2

134.82

Total

P11,468.88

* N, B. Cost of seedlings is broken down as follows:

Labour 20 t each;
materials 5 t each.

c) Maintenance: Compartment I

Watering: 8 litres/tree applied by watering can immediately after planting and thereafter 8 litres every 3 weeks until May, in the absence of rain. Assuming 3 applications, water is delivered to site by tractor and 5,000 litre bowser and stored in 1,000 litre galvanised tanks distributed along road lines.
Tanks may be moved as necessary.



Water 360 m3 @ P0.50/m3

180.00


Transport: 3 tractor hr./ha x 3

1,516.32


Labour: 10 man day/ha x 3

1,474.20

Weeding: 2 complete clear weedings by hand, including repairs and mulching of planting dishes, @ 10 man day/ha x 2

1,572.48

Termite Control: 1 application of 2.5 litres per tree of 0.2% Shelldrite solution.



Insecticide: 8 litres/ha = 75 litres @ P5.00/litre

375.00


Transport: 1 tractor hr/ha

168.48


Labour: 6 man days/ha

294.84

Fire Tracing: clear weeding by hand of 5 m wide external trace plus road margins: 0.482 ha @ 14 man days/ha

35.43

Total

P5.616.75

Total Year 1= P21,326.67

YEAR 2

Establishment: Compartment II (9.36 ha):

111,468.88

Maintenance:


Watering: Comp. I and II (18.72 ha):



Av. 24 litres/tree



Water: 720 m3 @ P5.00/m3

360.00


Transport: 3 tractor hrs/ha x 3

3,032.64


Labour: 10 man days/ha x 3

2,948.40

Weeding: Comps. I and II (18.72 ha)



2 complete clear weedings by hand, including repair and mulching of dishes, @ 16 man days/ha x 2

3,144.96

Termite Control: Comp. II - application of 0.2% Shelldrite solution @ 2.5 litre/tree.



Comp. I - contingency allowance of 20% of Year 1 costs



Insecticide: 90 litres @ P5.00/litre

450.00


Transport: 11 tractor hrs

198.00


Labour: 67 man days

351.75

Fence maintenance: contingency @ 5% of year 1 costs:



Materials

163.50


Transport

3.66


Labour

44.89

Road Maintenance: for 642 m of road:



Contingency at 10% of Year 1 costs



Labour

13.48

Fire Tracing: clear weeding by hand of 909 m of 5 m wide external trace plus 1284 m of road margins: 0.87 ha @ 14 man days/ha

63.95

Total year 2

P22,244.11

YEAR 3

Establishment: Compartment III (9.36 ha planted area) and excluding road construction

11,334.06

Road Construction: 266 m of 10 m wide road levelled by hand @ 1 man day/250 m2

55.86

Maintenance:


Watering: Comps II and III (18.72 ha): Av. 24 litres/tree



Water: 720 m3 @ P0.50/m3

360.00


Transport: 3 tractor hrs/ha x 3

3,032.64


Labour: 10 man days/ha x 3

2,948.40

Weeding: Comp. I: 1 clear weeding by hand @ 14 man day/ha

687.96


Comps II and III (18.72 ha): 2 clear weedings by hand, including repairs and mulching of dishes @ 16 man days/ha x 2

3,144.96

Termite Control:



Comp. III: 1 application of 2.5 litres per tree of 0.2% shelldrite solution.



Comps. I and II: contingency allowance of 20% of year 1 costs.




Insecticide 105 l at P5.00/litre

525.00



Transport 13 tractor hours

234.00



Labour 79 man days

414.75

Fence Maintenance: 5% contingency:



Materials

163.50


Transport

3.66


Labour

44.89

Road Maintenance: 1284 m of road @ 10% contingency cost;


Labour

26.96

Fire Tracing: clear weeding by hand of 1550 m external trace plus 1550 m road margins.



1.35 ha @ 14 man days/ha

99.25

Total Year 3.

£23,075.89

YEAR 4

Establishment: Compartment IV (9.36 ha) excluding road construction

P11,334.06

Road Construction: 250 m of 10 m wide road levelled by hand @ 1 man day/250 m2

52.50

Maintenance:


Watering: Comps III and IV



Water: 720 m3 @ P0.50/m3

360.00


Transport: 3 tractor hours/ha x 3

3,032.64


Labour: 10 man days/ha x 3

2,948.40

Weeding:



Comp. II: 1 clear weeding @ 14 man days/ha

687.96


Comps III and IV: 2 clear weedings @ 16 man days/ha

3,144.96

Termite Control: Comp IV - 1 application



Comps I, II and III - 20% contingency



Insecticide: 120 litres @ P5.00/litre

600.00


Transport 15 tractor hours

270.00


Labour 90 man days

472.50

Fence Maintenance: 5% contingency



Materials

163.50


Transport

3.66


Labour

44.89

Road Maintenance: 1550 m.@ 10% contingency:



Labour

32.55

Fire Tracing; 2200 m of external trace plus 1800 m of road margins:

142.59


1.94 ha @ 14 man days/ha


Total Year 4

P23,290.21

YEAR 5

Establishment: Compartment V (9.36 ha) excluding road constructions

11,334.06

Road Construction: Nil

-

Maintenance:


Watering: Comps IV and V



Water: 720 m3 @ P0.50/m3

360.00


Transport: 3 tractor hrs/ha x 3

3,032.64


Labour: 10 man days/ha x 3

2,948.40

Weeding:



Comp. III: 1. clear weeding @ 14 man days/ha

687.96


Comps IV and V: 2 clear weedings @ 16 man days/ha

3,144.96

Termite Control:



Comp. V: 1 application.



Comps I to IV - 20% contingency:



Insecticide: 135 litres @ P5.00/litre

675.00


Transport 17 tractor hours

306.00


Labour 101 man days

530.25

Fence Maintenance: 5% contingency:



Materials

163.50


Transport

3.66


Labour

44.89

Road Maintenance: 1800 m @ 10% contingency



Labour

37.80

Fire Tracing: 2850 m of external trace plus 1800 m of road margins = 2.33 ha @ 14 man days/ha

171.26

Total Year 5

P23,440.38

Year 6

Maintenance.


Watering: Compartment V



Water: 360 m3 @ P0.50/m3

180.00


Transport 3 tractor hours/ha x 3

1,516.32


Labour: 10 man days/ha x 3

1,474.20

Weeding: Comp IV: 1 clear weeding @ 14 man days/ha

687.96


Comp V: 2 clear weedings @ 16 man days/ha x 2

1,572.48

Termite Control: Comps I to V - 20% contingency



Insecticide 75 litres @ P5.00

375.00


Transport 9.5 tractor hours

171.00


Labour 56 man days

294.00

Fence Maintenance: 5% contingency



Materials

163.50


Transport

3.66


Labour

44.89

Road Maintenance: 1800 m @ 10% contingency



Labour

37.80

Fire Tracing: 2850 m external trace plus 1800 m road margins = 2.33 ha @ 14 man days/ha.

171.26

Total Year 6

P6,692.07

Year 7

Harvesting: Compartment I: trees should be sold standing to the local community who will fell and remove produce. Felling should be undertaken during the period October to December. Paid labour will be necessary to clean the compartment after exploitation by felling any remaining trees and cutting back any high stumps.


Labour: 5 man days/ha

245.70

Maintenance:


Weeding: Comp. V: 1 clear weeding @ 14 man days/ha

687.96

Termite Control: whole plantation - 20% contingency



Insecticide: 75 litres @ P5.00/litre

375.00


Transport: 9.5 tractor hours

171.00


Labour: 56 man days

294.00

Fence Maintenance: 5% contingency



Materials

163.50


Transport

3.66


Labour

44.89

Road Maintenance: 1800 m @ 10% contingency



Labour

37.80

Fire tracing: 2850 m external trace plus 1800 m road margins = 2.33 ha @ 14 man days/ha

171.26

Total year 7

P2,194.77

YEARS 8 to 21


Costs per Year

Harvesting:



One compartment should be clear felled each year starting with Compartment II in Year 8, Compartment III in year 9, etc, on a five year rotation. Costs as for Year 7:



Labour: 5 man days/ha

245.70

Maintenance:


Termite Control: whole plantation 20% contingency



Insecticide: 75 litres @ P5.00/litre

375.00


Transport: 9.5 tractor hours

171.00


Labour: 56 man days

294.00

Fence Maintenance: 5% contingency



Materials

163.50


Transport

3.66


Labour

44.89

Road Maintenance: 1800 m @ 10% contingency



Labour

37.80

Fire Tracing: 2850 m external trace plus



1800 m road margins = 2.33 ha @ 14 man days/ha

171.26

Total year 8

P1,506.81

Year 22

Harvesting: Final felling of Compartment I



Costs as for Yr. 7:



Labour: 5 man days/ha

245.70

Replanting:


Pre-planting; preparation of planting dishes in rows between rows of stumps 9.5 man days/ha

416.83

Planting: 1600 seedlings per hectare:



Seedlings @ 25 t each

3,744.00


Transport: 2.5 tractor hrs/ha

421.20


Labour @ 150 seedlings/man day

524.16

Fertilizer: for Yr 1.



100 Kg/ha @ P.15.00/50 Kg bag

300.00


Labour: 5 man days/ha

245.70

Beating-up (Blanking): as in Yr. 1



Seedlings: 2247 @ 25 t each

561.75


Transport; 0.5 transport hours/ha

84.24


Labour: 1.6 man days/ha

78.62

Maintenance:


Watering: as in Yr 1.



Water: 360 m3 @ P.0.50/m3

180.00


Transport: 3 tractor hrs/ha x 3

1,516.32


Labour: 10 man days/ha x 3

1,474.20

Weeding: as in Yr 1:



Labour 10 man days/ha

1,572.48

Termite Control: whole plantation: contingency at 20% Yr 1 costs



Insecticide: 75 litres @ P.5.00/litre

375.00


Transport: 9.5 tractor hours

171.00


Labour: 56 man days

294.00

Fence Maintenance: contingency cost of 5% Yr 1 costs:



Materials

163.50


Transport

3.66


Labour

44.89

Road Maintenance: 1800 m of roads at 10% contingency cost:



Labour

37.80

Fire Tracing: 2850 m of external trace plus road margins: 2.33 ha @ 14 man days/ha

171.26

Total: Year 22

P.12,676.31

COST SUMMARY

Year

Labour

Tractor

Materials

Seedlings

Total

1

9399.83

3396.09

4225.00

4305.75

21326.67

2

11692.56

4872.30

1373.50

4305.75

22244.11

3

12413.34

4909.30

1448.50

4305.75

32075.89

4

12516.66

4944.30

1523.50

4305.75

23290.21

5

12555.83

4980.30

1598.50

4305.75

23440.38

6

4282.59

1600.98

718.50

-

6692.07

7

1481.61

174.66

538.50

-

2194.77

8

793.65

174.66

538.50

-

1506.81

9

793.65

174.66

538.50

-

1506.81

10

793.65

174.66

538.50

-

1506.81

11

793.65

174.66

538.50

-

1506.81

12

793.65

174.66

538.50

-

1506.81

13

793.65

174.66

538.50

-

1506.81

14

793.65

174.66

538.50

-

1506.81

15

793.65

174.66

538.50

-

1506.81

16

793.65

174.66

538.50

-

1506.81

17

793.55

174.66

538.50

-

1506.81

18

793.65

174.66

538.50

-

1506.81

19

793.65

174.66

538.50

-

1506.81

20

793.65

174.66

538.50

-

1506.81

21

793.65

174.66

538.50

-

1506.81

22

5155.64

2196.42

1018.50

4305.75

12676.31


80609.16

29608.59

19983.50

25834.50

156035.75

Costs per planted hectare:


1722.2

632.66

427.00

552.02

3334.10

YIELD (m3) FROM 50 ha COMMUNITY WOODLOT MODEL

Year

1

2

3

4

5

6

7

8

9

10

11

12

13

14

15

16

17

18

19

20

21

22

Compartment























I

250*

-

-

-

-

-

393

-

-

-

-

360

-

-

-

-

307

-

-

-

-

245

II

-

250*

-

-

-

-

-

393

-

-

-

-

360

-

-

-

-

307

-

-

-

-

III

-

-

250*

-

-

-

-

-

393

-

-

-

-

360

-

-

-

-

307

-

-

-

IV

-

-

-

250*

-

-

-

-

-

393

-

-

-

-

360

-

-

-

-

307

-

-

V

-

-

-

-

250*

-

-

-

-

-

393

-

-

-

-

360

-

-

-

-

307

-

Cumulative Total

250

500

750

1000

1250

1250

1643

2036

2429

2822

3215

3575

3935

4295

4655

5015

5322

5629

5936

6243

6550

6795

* Obtained from clearance of indigenous woodland.

INDIRECT COSTS. DIRECT COSTS AND YIELDS: 50 ha COMMUNITY WOODLOT MODEL

(Assuming unskilled labour paid at drought relief rates of P.2.00 per day.)

Year

Protection & Supervision

Management

Direct Costs

Total Costs

Total Yield


Salaries

Salaries

Vehicle

Building Maintenance

(Pula)

(Pula)

(m3)

1

2,920

1,135

503

170

21,327

26,055

250*

2

2,920

1,135

503

170

22,244

26,972

250*

3

2,920

1,135

503

170

23,076

27,804

250*

4

2,920

1,135

503

170

23,290

28,018

250*

5

2,920

1,135

503

170

23,440

28,168

250*

6

2,920

1,135

503

170

6,692

11,420

-

7

2,920

1,135

503

170

2,195

6,923

393

8

2,920

1,135

503

170

1,507

6,235

393

9

2,920

1,135

503

170

1,507

6,235

393

10

2,920

1,135

503

170

1,507

6,235

393

11

2,920

1,135

503

170

1,507

6,235

393

12

2,920

1,135

503

170

1,507

6,235

360

13

2,920

1,135

503

170

1,507

6,235

360

14

2,920

1,135

503

170

1,507

6,235

360

15

2,920

1,135

503

170

1,507

6,235

360

16

2,920

1,135

503

170

1,507

6,235

360

17

2,920

1,135

503

170

1,507

6,235

307

18

2,920

1,135

503

170

1,507

6,235

307

19

2,920

1,135

503

170

1,507

6,235

307

20

2,920

1,135

503

170

1,507

6,235

307

21

2,920

1,135

503

170

1,507

6,235

307

22

2,920

1,135

503

170

12,676

17,404

245


64,240

24,970

11,066

3,740

156,038

260,054

6,795

* Yields obtained from clearing indigenous woodland prior to planting.
Cost per m3 = P.38.27
Ind. Costs = 66.7% Direct Costs.

Total Costs and Yields Discounted at 5%: 50 ha Community Woodlot Model

Year

Total Costs (Pula)

Total Costs Discounted

Total Yield (m3)

Total Yield Discounted

1

26,055

26,055.0

250*

250.0

2

26,972

25,687.6

250*

238.1

3

27,804

25,219.1

250*

226.8

4

28,018

24,203.1

250*

216.0

5

28,168

23,173.8

250*

205.7

6

11,420

8,947.9

-

-

7

6,923

5,166.1

393

293.1

8

6,235

4,431.1

393

279.2

9

6,235

4,220.1

393

265.9

10

6,235

4,019.1

393

253.2

11

6,235

3,827.7

393

241.1

12

6,235

3,645.5

360

210.5

13

6,235

3,471.9

360

200.5

14

6,235

3,306

360

191.0

15

6,235

3,149.1

360

181.9

16

6,235

2,999.2

360

173.2

17

6,235

2,856.3

307

140.3

18

6,235

2,720.3

307

133.6

19

6,235

2,590.8

307

127.3

20

6,235

2,467.4

307

121.2

21

6,235

2,349.9

307

115.4

22

17,404

6,247.0

245

87.9


260,054

190,754.5

6,795

4,151.9

Discounted total costs

= P.45.94/m3
= P.54.70/air dry tonne**

* Yields obtained from clearing indigenous woodland prior to planting.
** The density of air dry wood at 35% moisture content is taken as 840 Kg/m3.

A5.4 Indigenous Woodland Management

The Mean Annual Increment (MAI) of Mophane woodland is estimated to be 2.42. air dry tonnes (at 35% mc)/ha/year. Some of this increment will be lost through the effects of fire, disease and possibly unauthorised felling, and it is therefore considered prudent to restrict exploitation of this woodland type to 65% of the MAI, i.e. 1,573 tonnes of fuelwood each year.

The costs of management consist of four components, namely the costs of protection, harvesting, supervision and management. Table A5.4 (c) gives a breakdown of the costs, at present day rates, of each component annually for a twenty year period.

To protect each 1,000 ha block from unauthorised clearing or felling, four Forest Guards will be required. The guards should be recruited locally and paid the minimum government wage of P 4.55 per day, seven days a week (P 1,638 per year).

Harvesting will be undertaken annually over a three month period. It is estimated that one air dry tonne can be harvested per man day (including, felling, crosscutting and stacking). Thus 1,573 man days of labour will be required each year for each block. This will generate considerable employment opportunities.

During harvesting, two supervisors will be required for a three month period. Supervisors should be junior technical grade foresters. Each supervisor will require a motorcycle costing about P 3,000 and provision is also made in this model for renting two local houses and an office room for the harvesting period at P 75/month each. With a three month harvesting period, two supervisors will be able to control harvesting operations in four blocks. During the remaining nine months of the year, periodic visits by a supervisor, estimated at 2 man days/month, will be necessary to ensure adequate protection of a block. Supervisors' salaries are in the region of P 4,500 per year.

It is assumed that the management of these 1,000 ha blacks will be controlled by a professional forest officer through a District Office. The. cost of. management will be constant throughout the twenty year period covered by this model and thus the management cost per air dry tonne will decrease as more blocks are brought under management.

The Staff of the District office will consist of:

1 Forest Officer Pula

6,500 per year

1 Accounts Clerk

3,500 per year

1 Clerk/Typist

4,500 per year

1 Driver

2,150 per year


16,650 per year

In addition, one 4x4 vehicle will be required, for which the annual costs are estimated at P7,380. Maintenance of office buildings is further estimated at P2,500 per year.

Table A5.4 (a) - Management of the Indigenous Woodland (Mophane)
Costs (Pula) and Yields (Air Dry Tonnes)

Year

Supervision

Management

Direct Costs

Total Cost

Total Yield

(F. G. Wages)

Salary

Vehicle

House/Office

Salaries

Vehicle

Buildings

(Harvesting)

(Pula)

(Tonnes)

1

7,665

2,557

1,775

675

16,650

7,380

2,500

8,258

47,460

1,573

2

15,330

5,114

3,546

1,350

16,650

7,380

2,500

16,516

68,386

3,146

3

22,995

7,671

5,319

2,025

16,650

7,380

2,500

24,775

89,315

4,719

4

30,660

10,228

7,092

2,700

16,650

7,380

2,500

33,033

110,243

6,292

5

38,325

12,785

8,865

3,375

16,650

7,380

2,500

41,291

131,171

7,865

6

45,990

15,342

10,638

4,050

16,650

7,380

2,500

49,550

152,100

9,438

7

53,655

17,899

12,411

4,725

16,650

7,380

2,500

57,808

173,028

11,011

8

61,320

20,456

14,184

5,400

16,650

7,380

2,500

66,066

193,956

12,584

9

68,985

23,013

15,957

6,075

16,650

7,380

2,500

74,324

214,884

14,157

10

76,650

25,570

17,730

6,750

16,650

7,380

2,500

82,583

235,813

15,730

11

84,315

28,127

19,503

7,425

16,650

7,380

2,500

90,841

256,741

17,303

12

91,980

30,684

21,276

8,100

16,650

7,380

2,500

99,099

277,669

18,876

13

96,645

33,241

23,049

8,775

16,650

7,380

2,500

107,357

295,597

20,449

14

107,310

35,798

24,822

9,450

16,650

7,380

2,500

115,616

319,526

22,022

15

114,975

38,355

26,595

10,125

16,650

7,380

2,500

123,874

340,454

23,595

16

122,640

40,912

28,368

10,800

16,650

7,380

2,500

132,132

361,382

25,168

17

130,305

43,469

30,141

11,475

16,650

7,380

2,500

140,390

382,310

26,741

18

137,970

46,026

31,914

12,150

16,650

7,380

2,500

148,649

403,239

28,314

10

145,635

48,583

33,687

12,825

16,650

7,380

2,500

156,907

424,167

29,887

20

153,300

51,140

35,460

13,500

16,650

7,380

2,500

165,165

445,095

31,460

1,606,650

536,970

372,330

141,750

333,000

147,600

50,000

1,734,234

4,922,534

330,330

Over the twenty year period covered by this model, twenty blocks will have been brought under management, covering 20,000 ha. The total production of fuelwood for this period will be 330,330 air dry tonnes (at 35% me). The economic cost of wood from such a natural woodland management model would be 1.5 t/kg.

A summary of the costs and yields associated with this scheme is given in Table A5.4 (a).


Previous Page Top of Page Next Page