7.1. Introduction
Road maintenance is essential in order to (1) preserve
the road in its originally constructed condition, (2) protect adjacent
resources and user safety, and (3) provide efficient, convenient travel
along the route. Unfortunately, maintenance is often neglected or improperly
performed resulting in rapid deterioration of the road and eventual failure
from both climatic and vehicle use impacts. It follows that it is impossible
to build and use a road that requires no maintenance.
In order to plan for road maintenance needs, it is important
to keep a complete set of "as built" plans and records of all maintenance
operations and observations. The as built plan should contain the following:
- Complete job index
- Complete history of project from planning stage to construction
- Photographic records
- Exact location and observations of any unstable conditions in relation
to the road location
- Exact location of culverts and other drainage features
- Wet areas that may have required additional excavation and replacement
with more suitable ballast backfield materials
- All major changes made to the original plan
Probably the most valuable tool for any maintenance program
is the knowledge and experience gained by individuals performing the maintenance.
Every effort should be made to retain competent, knowledgeable, and experienced
individuals in these positions not only from the standpoint of instituting
and executing a good maintenance program, but for future road planning
needs as well.
In deciding on an appropriate level of maintenance for
a particular road or road segment, consideration must be given to the
amount and type of vehicle use and physiographic and climatic variables
which may impact drainage structures. A useful guide to the types and
frequency of maintenance activities appropriate for a given road is shown
in Table 43.
7.2 Drainage System Maintenance
Drainage structures must be kept free of debris and obstructions.
On newly constructed roads, or in upstream areas where heavy earth moving
is taking place (e.g., urban development, logging, mining, etc.), cleaning
may have to be more frequent.
Grass growing in ditches, unless it is dense enough to
cause a major impediment to flow, should not be removed during cleaning.
Likewise, shoulder and cut banks must not be undercut.
Table 44. Typical road maintenance activities appropriate
for a given road use level.
Management
Decision for Road
|
Types of Activities
That Could Be Expected
|
Always open
|
- Regularly scheduled running surface reshaping or repair
- Regularly scheduled ditch and culvert cleaning, repair
- Yearly brush, tree, snag safety check, removal
- Yearly stream trash removal around channel crossings
- Yearly reseeding and/or fertilizing of cut and fill slopes
- Yearly fence, cattle guard check
- Snow thaw road check and repair
- Storm damage and pollution control structure check and repair
- Seasonal check of signs and notices
|
Closed-usable
|
- Periodic dust control near inhabited or work areas
- Pre and post rainy season channel crossing
and ditch maintenance
- Storm damage and pollution control structure
check and repair
- Yearly brush, tree, snag safety check,
removal
- Yearly reseeding and/or fertilizing of
cut and fill slopes
- Periodic check of closure controls and
signs
- Yearly fence, cattle guard check
|
Closed-not usable
|
- Pre and post rainy season channel crossing and
ditch maintenance
- Yearly stream trash removal around channel
crossings
- Yearly inspection and maintenance of drainage
structures
- Road outsloped and/or water barred; channel
crossings usually removed
- Periodic check of closure controls and
signs
|
Reactivate-unusable
|
- Reconstruct channel crossing structures (culverts,
etc.)
- Reinstall ditches and cross drains, if
needed
- Clear debris, slides, trees; remove hazard
trees and brush
- Regrade and finish road surface
- Sign and post as needed
- Check, repair, or install fence as needed
- Reconstruct road to higher standard if
necessary
|
The objective in "pulling a ditch" is to grade the ditch
so as to clean it of debris that could divert flow from the ditch on to
the road surface. Hand clearing with a shovel is effective when the work
load is light or the presence of structures (e.g. cross drains or culvert
inlets) make it impractical to use heavy equipment. With a grader, the
following procedure is followed:
1. Flag all culverts and cross drains
2. Remove snags, rocks, and other hazards before grading begins
3. Cut only the ditch bottom and shoulder; avoid undercutting
the cut slope; do not redress the cut slope
4. Spread fines into the road with surface reworking
5. Avoid working around culverts or other channel crossing structures
so as to minimize damage to inlets
Debris in and around culverts should be removed by hand
or by grapples or tongs rather than by heavy equipment working directly
in the stream. Stream channels should be completely free of floatable
debris (branches, leaves, small logs, construction material, garbage,
etc.) for at least 30 m (100 feet) upstream. If plugging of a particular
culvert occurs frequently and a debris deflector or "trash rack" was not
included in the original design, one should be installed as part of the
maintenance program.
7.3 Road Surface Maintenance
Road surfaces should be reworked only
as necessary to provide a smooth running surface and a good crown or slope
for drainage. All-season roads will require continual monitoring for surface
and subgrade wear or deterioration. Rutting and loss of ballast often
occur during rainy season use. Snow removal equipment can also destroy
the road surface by removing or altering the crown and removing ballast.
A plan should be in place to provide ballast when necessary to maintain
continued use of the road.
On non-surfaced roads, a grader on the first pass should
move material from the shoulder to a windrow in the center of the roadway.
On the second pass, the blade should be centered on the windrow and continue
working along the roadway. The blade should be adjusted so as to provide
a slight slope or crown and should avoid cutting too deep into the road
surface. Any excess material should be stored in the berm--not sidecast
over the edge of the fill.
A wide variety of chemicals are commonly used to treat road surfaces
to minimize wear, reduce dust, or de-ice. However, many of these products
provide only minimal benefit and represent a potential hazard to water
quality (US Environmental Protection Agency, 1975). Oil based dust palliatives
must be used very carefully where the potential for entering surface or
groundwater exists. Likewise, salts such as sodium chloride (NaCI) and
calcium chloride (CaCl2), along with additives to prevent caking, rust,
and corrosion, can cause acute and chronic toxicity in aquatic organisms
and fish, contamination of groundwater supplying public and domestic water
users, and death to vegetation adjacent to the road. Maximum salt concentrations
can be found at soil surfaces nearest the road, but because they can be
readily leached, salts can easily enter groundwater. High concentrations
of salts have been found in streams during dry season low flows when the
major component contributing to stream flow consists of groundwater.
Sulfite waste liquor from pulping operations is used
extensively for dust abatement, however, it too has a potential for adversely
impacting water quality through its high biochemical oxygen demand. Fortunately,
though, the BOD-containing agents in pulping liquors will oxidize rapidly
on the road surface. Controlled application during dry weather to prevent
runoff will minimize impacts.
Herbicides used to control roadside vegetation represent the final class
of road maintenance compounds that present a potential health or water
pollution hazard if used incorrectly. Compounds such as dioxin, contained
in 2,4-D and 2,4,5-T, are extremely toxic even in minute quantities.
Practices and methods to help minimize impacts from road chemicals include:
-
control application. Use only as much
chemical as needed, both in concentration and rate of application,
to provide the desired effect. Chemical manufacturers provide detailed
information on the label of the container concerning dilution requirement,
application rate and method, worker safety precautions, spill cleanup
procedures, and other useful information. Be aware of weather conditions.
Do not apply chemicals immediately prior to or during rainfall. Provide
adequate training, performance standards, and supervision of application
personnel and equipment. Perform trial applications to determine if
calculated application rate is adequate. Keep records of chemical
compounds used, the target species identified, concentration and application
rates, vegetative growth stage (pre- or post-emergent), any unusual
vegetative or environmental factors present during the application,
and results of the application.
-
Use extra caution near streams. Avoid
applying chemicals where the road crosses a channel and for 20 m (60
ft) on either side. If necessary, provide a filter strip between the
road and the stream. Prevent spillage near or into streams. Do
not, under any circumstances, discharge unused chemical
into a stream.
-
Disposal of excess chemical and container treatment.
Clean and rinse equipment and storage containers in an area where
waste water can be safely collected and treated. If necessary, collect
and ship excess hazardous chemicals to an authorized hazardous waste
disposal facility.
7.4 Emergency Storm Response
An effective way of dealing with storm damage to roads
and property is to provide for an emergency response program in which
personnel and equipment can be mobilized as needed on short notice. This
concept is similar in practice to that dealing with emergency measures
used in fire control. The purpose of the plan is to:
1. Prevent loss of life or injury
2. Prevent damage to soils, streams, fisheries, and other resources
3. Prevent and/or minimize damage to capital improvements, private property,
roads, and other features
4. Provide for efficient, economical, and necessary use of available
finances, equipment, and personnel
5. Evaluate structural and resource damage when it occurs and determine
needs for corrective measures to prevent further damage
Necessary items to include in a storm response action plan are:
1. A system to collect and analyze weather, soil, and road conditions
2. A communication system between personnel responsible for activating
the storm action plan
3. Establishment of organizational plans and responsibilities for prevention
and control of storm damage
4. Methods of financing and documenting costs of personnel and equipment;
outline of individuals authorized to use finances, personnel, and equipment
5. Telephone numbers for providing public information and communication
with law enforcement and other public agencies
6. Provisions for monitoring the effects of storms and efforts to prevent
damage; reconnaissance and estimates of extent of damage to structures
and resources; preliminary cost estimates
7. Storm damage reporting procedures
Weather data should be collected daily and should include
daily amounts of precipitation, cumulative precipitation per storm, total
per season, month, etc. Any information indicating run-off amounts, snow
pack accumulation/melt rates, temperature, temperature changes, wind and
barometric pressure should be noted. Additional or more frequent information
updates can be requested as conditions warrant. A rating system for storms,
such as that used for fires, can be developed based on historical data
and/or local knowledge. For each condition, a specific set of activities
ranging from observation to full region-wide patrols and work teams will
be identified.
7.5 Road Abandonment and Reclamation
Forest roads are often designed for temporary or intermittent
use in which two situations may exist: (1) the road is planned for closure
with the intent of reconstructing at some point in the future, or (2)
the road is planned for permanent closure. In the first instance, if the
interval of non-use is relatively short, a physical barricade blocking
all entrances to the road may be all that is required provided that periodic
checks are made throughout the non-use period to ensure that road drainage
structures, erosion control measures, and other slope protection measures
are functioning properly. A barricade may consist of a locked gate or
a variety of crude barriers constructed of native materials--rock, slash,
cull logs, etc.
If periodic checks and maintenance cannot be performed
(e.g. during heavy snow pack conditions) other measures in addition to
barricading need to be taken. These measures might include installing
a system of rolling dips or water bars, outsloping, and stabilizing all
cut and fill slopes (see Chapter 4). Scarification and revegetation of
exposed surfaces, including the roadway itself, may be appropriate depending
on the type of road surface, the potential for erosion, and the non-use
period.
When an extended non-use period is planned and the risk
of environmental damage from failure is significant, a partial restoration
of the original ground profile may be considered. The objective here is
to convert a portion of surface water flow back to subsurface flow and
to provide more efficient surface runoff capacity. An effective method,
called "Kanisku" closure, can be used on sideslopes less than 60 percent
and is illustrated in Figure 121. If terrain and road conditions permit
the use of this technique without significant loss of soil over the edge
of the fill, this procedure can be accomplished with an angle-blade bulldozer.
This technique is not
appropriate on end haul constructed roads, on ballasted or surfaced roads,
on some soil types, or in regions with high precipitation.
Figure 121. "Kanisku" closure is effective
on side cast constructed roads on slopes up to 60 percent in areas with
low to moderate precipitation.

Stream crossings on intermittent-use roads require special
attention. In addition to guidelines presented elsewhere in this book,
design, construction, and maintenance considerations for intermittent-use
roads include:
-
Minimize the amount of culvert fill.
-
Use generous culvert end area estimates.
-
Design for permanent installation.
-
Plan for supplemental maintenance checks if there is any doubt as
to the ability of the installation to withstand heavy storm events.
-
If a stable installation is technically or economically infeasible,
include subsequent culvert removal if it can be accomplished with
minimal water quality impact. If not, avoid the site.
Temporary log stringer bridges can be used when a stream
crossing installation would require a large amount of fill. With short
non-use periods, it may be more economical to design a "longer life" temporary
bridge and leave it in place. With longer non-use periods, it is advisable
to use a minimal cost structure and remove it after use.
For channel crossing structures that have functioned
satisfactorily for years, the best solution, in most cases, is to leave
it in place and restore it to its original condition (remove debris, clean
ditches, revegetate side slopes, reshape road surface crown). For those
crossings having a high failure risk, continued maintenance or partial
or entire removal are the only choices, difficult as they may be. If removal
is chosen, the use of proper equipment and attention to timing can aid
in reducing the severity of water quality impacts. If total removal cannot
be accomplished for technical or economic reasons, a possible solution
is a relief dip in the culvert fill (Figure 122). A relief dip does not
preclude the need for stabilization, but, rather, reduces the water quality
impact upon failure by directing the course of overflow water and reducing
the amount of available sediment.
In the case of permanent closure, methods described above
may be appropriate, making sure that all culverts and bridges are removed
and excess fill is hauled to a safe disposal area. Additionally, it is
also desirable to break up the road surface with deep penetrating hydraulic
ripper teeth. This aids in restoring soil permeability and enhancing revegetation.
For esthetic reasons, it may be desirable to completely
restore the original ground profile, or "deconstruct" the road. One way
to accomplish this is to temporarily store excavated material and then
pack it back into the roadway following use. More commonly, excavated
material is side cast, and following use, pulled back up into the road
prism with hydraulic shovel or dragline. On slopes greater than 60 percent,
it is highly recommended that excavation and side cast pullback
be accomplished during the same dry season. After deconstruction, the
site is revegetated including tree establishment where appropriate. Follow-up
planting or fertilizing may be necessary for several years following restoration.
Figure 122. Relief dip reduces the
potential impact of culvert failure by reducing the amount of potential
sediment.