NumberDescriptionSize
(m2)
Estimated cost
(U.S.$)
    
 Administration  
1Offices -Centre Director152 250
1 Administrator121 800
1 Administrative aid101 500
6 Secretaries365 400
1File room152 250
1Copying room and store for office supplies and equipment121 800
1Mail room  4   600
1Meeting room507 500
16  Staff offices8012 000  
30  Student study and working rooms9013 500  
1Library100  15 000  
1Classroom9013 500  
1Audiovisual laboratory355 250
    
 Store rooms  
1For chemicals ($115/m2)121 380
1For fertilizers, rotenone, lime, etc. ($115/m2)404 600
1
For field equipment and supplies (including nets, outboard motors, boats, etc.)
(Roof, side columns and concrete floor, with wind breakers or aluminium curtains on three sides) ($90/m2)
125  11 250   
1For feeds ($115/m2)505 750 
1Annex to the farm laboratory ($150/m2)8012 000   
    
 
Workshop (including mechanic, electrician, plumber, carpenter, technician and tool shops), garages, area for small fuel station.
(Buildings approximately 150 m2. Remainder of facilities with roof, side columns, concrete floor, wind breakers or curtains; approximately 450 m2.)
  
    
1Buildings at $150/m2150  22 500   
1Other structures at $90/m2450  40 500   
    
 Laboratories  
1Water chemistry and soil analysis609 000
Fish nutrition (dry-wet labs, office, food technology room, etc.)180  27 000  
1Disease (dry-wet labs, office)100  15 000  
1Limnology609 000
Training - core laboratory for student training ($150/m2)9013 500  
1Reference museum9013 500  
1Feed mill630  94 500  
  Sub-total361 830    
    
 Staff residences and hostel  
15  Residences ($150/m2)1 950     292 500     
1Hostel ($150/m2)900    135 000     
  Total789 330     