6. IMPLEMENTATION

6.1 Timescale for implementation and development

(85) An outline timescale for the project is shown in Figure 29. To permit a relatively rapid development, it would be appropriate to phase the project in a manner ensuring early completion of critical facilities. Thus research activities may be initiated before the final completion of the whole project. This is particularly critical as the timescale indicates that it may be difficult to complete substantial parts of the construction during the coming dry season (November 1986-June 1987).

(86) A more detailed timescale for the initial phases of the project is shown in Figure 30. This is in the form of a simplified critical path chart, and identifies the significant points in the current implementation. Table 32 defines the critical factors likely to cause delay. Table 33 defines the separate phases and the approximate order of execution of the sub-sections within each phase. These may conveniently, but not necessarily be let out as separate contracts.

Table 32 - Significant delaying factors

1 Supply of materials;
2 Completion of soil tests/foundation problems;
3 Completion of land purchase/approvals/registration;
4 Supervision resources in FRI;
5 Specification changes/unclear design detail;
6 Unusual weather conditions;
7 Construction quality, supervision, fitness of construction equipment;
8 Conflicts between separate contractors over scheduling, material supply, security and control.

6.2 Budget targets

(87) The design as defined has been costed using current PWD rates and current estimates for aquaculture components. The outline total is shown in Table 34, compared with the current allocation. Details of the costing are given in Annex G. As this demonstrates, the project is just within the budget if full contingencies are allocated.

(88) In the event that the development costs cannot be contained within the allocation, whether through unexpected site costs, through inflationary effects during the project timescale, or other causes, Table 35 identifies the areas in which some savings may be made. As the bulk of the project cost lies in the residences, an initial reduction in the staff establishment, and the greatest possible use of local staff will have a positive effect on the budget.

Figure 29

Figure 29 - Outline implementation timetable for BFRS

Figure 30

Figure 30 - Flowchart of critical events during BFRS development

Table 33 - Phasing of BFRS development

OBJECTIVES:Provide as early as possible a functioning research environment defined by:  - Working ponds;
 - Basic research facilities;
 - Water, power, air supplies, incl. fresh water;
 - Accomodation.
CONSTRAINTS:Require facilities for senior staff;
Require secure land area, free of flooding;
Problems of ‘weather window’ November - July.

PROPOSAL (in order of priority):

 PHASE ACTIVITY:
1Land/site preparation:aEstablish site base, temporary wall around building area;
bMain wall, access track;
cDevelop smaller ponds - water from khal;
dBuild main gate/sluice;
eDevelop other ponds;
fComplete supply/drainage channels;
gFinish all internal gates;
hFinish road to building area.
    
2Laboratory buildings:
     (part 1)
aHatchery laboratory;
bServices building;
cAnalytical laboratory.
    
3Residential buildings:
     (part 1)
aGuesthouse
bType B
cType C,D,E (40%)
    
4Administrative blding:aComplete building.
    
5Residential buildings:
     (part 2)
aType F,G (60%).
  
    
6Laboratory buildings:
     (part 2)
aToxicology/pathology;
bDemonstration laboratory.
    
7Residential buildings:
     (part 3)
aType C,D,E (60%);
bType F,G (40%).
 
8Landscaping/finishing.

Table 34 - Budget approximations

COMPONENTQUANTITYCOSTTOTAL, Taka × 1000
1.Land70 acres75,0005,250
2.Earthworks   
Main supply, wall
 420,000 
Main drain
 40,000 
Secondary supply
 210,000 
Secondary drain
 16,000 
l ha ponds
 210,000 
0.5 ha "
 330,000 
0.2 ha"
 310,000 
0.1 ha "
 300,000 
Miscellaneous ponds
 160,000 
Building area
 240,000 
Fill material, excavation
 2,000,0004,236
3. Water control   
Main gate
 360,000 
Pumping station*
 30,000** pumps excluded
Secondary gates
 600,000(in eqt. budget)
Tertiary gates
 900,000 
Drain outlets
 600,0002,490
4. Water supply, services   
Saline water
 300,000 
Tubewell
 40,000 
High quality system
 150,000 
Storage tanks
 300,000 
Septic tank
 250,0001,040
5. Buildings   
Administration
 3,100,000 
Laboratories
   
Analytical
 1,900,000 
Toxicology
 1,430,000 
Demonstration
 600,000 
Hatchery
 2,100,000 
Services
 1,200,000 
Rest house
 1,350,000 
Residences
   
B
 1,350,000 
C
 2,100,000 
D
 3,400,000 
E
 1,350,000 
F
 4,200,000 
G
 1,250,00025,330
6. Services   
Electrical, at 8% of (5)
 2,026,000 
Plumbing, at 6% OF (5)
 1,520,000 
Airconditioning, at 5% OF (5)
 1,267,000 
Cold store
 200,0005,013
7. Site works   
Road, 1000m, at 800/m
 800,000 
Bridges
 400,000 
Wall protection
 100,000 
Fences, huts
 200,000 
Landscaping
 300,0001,800
TOTAL  45,159

Table 35 - Potential project cost savings

AREA OF SAVINGNOTE
   
1)POND AREA- Little overall effect on cost
- Develop part of ponds only in early stages- Little overall effect, but could be completed easily later
- Reduce size of S-wall- Savings in land used, but poorer security
- Supply water from Khal- Saves supply canal, moderate effect on cost
- Smaller ponds and wall- Could save some land and construction cost
- Do not install pumps- Could easily be done later
   
2)LAB FACILITIES- Slightly more effect
- Combine analytical and toxicology/disease labs- Some savings, though less potential for work; feasible
- Simplify buildings- Possible; could reduce specification in hatchery and demonstration lab
- Reduce lab sizes- Not desirable; better have fewer labs of good size
   
3)SERVICES-Some savings possible
- Single field water supply- Less convenient, but possible
-Reduced level of services- Possible, if expandable later
   
4)ACCOMODATION- Greatest effects on cost
- Reduce staff establishment- Reduced capacity, but selection of good staff could compensate
- Recruit more local staff- Possibly better staff morale
   
5)OTHER- Variable effects on cost
- Reduce administration function- Greatest effects are on accomodation
- Increase contract supervision- Possible savings, but needs considerable commitment

6.3 Acquisition of land

(89) The actual land area required, as defined on the site layout is summarized in Table 36. Table 37 summarizes the land available in the outline survey area as defined in Figure 31, and shows the areas of the khal and the strip of land lying to the north of the khal, both of which might be excluded from purchasing. The site area should be surveyed as soon as possible, to confirm the accuracy of current site maps and to define ownership of areas required. Where possible, the boundary should be adjusted to conform with existing boundaries of holdings.

Table 36 - Actual land area requirements

COMPONENTDIMENSIONS,mAREA,m2
Main wall13m × 820m10,660m2
Borrow area37    × 82030,340
Main supply  7    × 7004,900
Internal wall  7    × 7004,900
Sec. supply  4    × (250 × 5)5,000
Sec. drain  4    × (250 × 4)4,000
Ponds 1 ha  3    × (168 × 63)31,406
0.5 ha
  9    × (128 × 43)48,769
0.2 ha
18    × (68 × 33)39,488
0.1 ha
27    × (53 × 23)31,894
Buildings and other90    × 35031,500
TOTAL242,900 m2 = 59.99 acres

Table 37 - Areas of site zones

SITE ZONESAREA, haacres
1) Overall30.3875.0
2) Khal1.353.3
3) Borrowpit3.308.2
4) Fringe N of khal1.303.2
1 - (2+3+4)24.4360.3
1 - (4)29.0871.8
Figure 31

Figure 31 - Land allocation map - proposed site area

6.4 Selection of consulting engineers

(90) A draft call for tender for consulting engineers, with terms of reference and schedule of works if provided in Annex H. Selection would be based on prior qualification and quality of technical proposals. Financial terms would be negotiated with the company or group offering the best technical proposal. A single firm would be employed for the entire contract, including design and supervision, though FRI would normally reserve the right to exclude parts of the terms of reference and schedule of works if necessary.

6.5 Selection of contractors

(91) This would ideally proceed within several weeks of the selection of consulting engineers, with the letting of the first phases of the development, permitting the initial site development to proceed, and preparing the site for building work. Table 38 summarizes some of the critical aspects of selection. This would normally be done on the basis of quoted rates for schedules of work, but should be strongly conditional on evidence of satisfactory work of a similar nature, and evidence of capacity for the work involved on the timescale specified. If possible a similar approach should be adopted to that of the selection of consulting engineers, in that a technical evaluation be the prime selector.

Table 38 - Factors affecting selection of contractors

- Financial standing, references;
- Local experience, base in region;
- Record of work at similar scale;
- Clients references;
- Specific experience in area of contract;
- Proven ability to work with other contractors on multi-contract project;
- Good project documentation;
- Good supervisory and foreman staff;
- Good organization of materials supply and quality;
- Good record of time and schedule keeping;
- Good record of labour management;
- Full certification of any skilled trades.

Note: The first contractor, carrying out site clearing and development will be required to provide site office and temporary storage.

6.6 Project specifications

(92) Details of specifications are given throughout the report, together with further detail in the Annexes. It is expected that design and construction follows good national practice and that materials and workmanship will be subject to testing at any stage.

Some specific recommendations known to be relevant in these circumstances are given in Table 39.

Table 39 - Specific precautions in project development

 
  1. Ensure good communication and co-operation between contractors;
  2. Ensure adequate foundation design, particulary for main sluice gates and taller buildings;
  3. Avoid using site materials for concrete;
  4. Store other materials to avoid salt contamination;
  5. Don't use local water for concrete, unless mass concrete where appearance not critical;
  6. Use if at all possible good quality fresh water;
  7. Cure concrete properly, shade and moisten to avoid heat stress and rapid curing;
  8. Provide a secure material and equipment store and compound;
  9. Keep plastic pipes and fittings out of direct sunlight;
  10. Store all pipes, tiles, blocks, etc. properly and securely;
  11. Trench, lay and cover pipes correctly, mark positions;
  12. Mark and record all work, particularly networks positions;
  13. Provide adequate provision for rainwater runoff in both temporary and permanent works;
  14. Build larger walls in several stages, allow for contraction and compaction;
  15. Remove organic topsoil if present, use 50 × 50 mm minimum puddle trench on main walls;
  16. Turf properly, break clods and lumps from excavated areas, remove roots if present;
  17. Make sure any anti-seepage measures are correctly taken.

6.7 Project direction

(93) It is recommended that a capable senior member of FRI staff be allocated as soon as possible to provide the essential direction of the project on behalf of FRI. As this is a significant project of considerable technical diversity, it is essential that a widely experienced and professionally competent individual be given the responsibility, which should be full-time committment for the duration of the project implementation.