TOPOGRAPHY
Survey completed
SOILS
Design soils testing programme
Take soil samples
Laboratory analysis
Soils evaluation, foundation analysis
PLANNING
Develop master plan for pilot aquaculture project, Phase I
Locate existing construction and road work
Locate water supply and drainage features
POND DESIGN
Determine design criteria - biological and engineering
Decide on location
Prepare preliminary designs
Materials and alternatives study
Preliminary cost estimates
Final design and cost estimates
WATER SUPPLY AND WASTE DISPOSAL
Consult with hydrologists and agriculture engineers on groundwater and shoreline conditions
Evaluate saltwater source alternatives
Develop water quantity requirements
Drill test well or sink caisson
Develop waste water requirements
Prepare preliminary designs
Materials and alternatives study
Preliminary and cost estimates
Final design and cost estimates
CONTRACT DOCUMENTS
Final construction drawings
Final construction specifications
Construction cost estimates and project schedule
ENGINEERING SCHEDULE, 1 TO 30 SEPTEMBER 1983