8. TOPOGRAPHICAL SURVEYS - DIRECT LEVELLING

8.0 Introduction

1. In Chapters 5 and 6, you learned about various devices for measuring height differences. You also learned how to use these devices to solve three types of problems in measuring height differences, which you may face when you plan and develop a fish-farm (see Section 5.0). Now, you will learn how to plan surveys to solve these problems, how to record the measurements you make in your field-book, and how to find the information you need from these measurements.  
70.GIF (5880 byte)
     

What are elevation and altitude?

2. You have learned what the height of a ground point is. Now, however, you will need to know a more accurate definition of this term.

  • When the height of a point is its vertical distance above or below the surface of a reference plane* you have selected, it is called the elevation* of that point.
  • When the height of a point is its vertical distance above or below mean sea level (as the reference plane), it is called the altitude* of the point.

Example

Elevation of a point above a selected ground mark A
Altitude of the same point above mean sea level (amsl)

1.83 m
345 m


3. The vertical distance between two points is called the difference in elevation , which is similar to what you have learned as the difference in height (see Section 5.0). The process of measuring differences in elevation is called levelling , and is a basic operation in topographical surveys.

 
70a.GIF (6745 byte)
     

What are the main levelling methods?

4. You can level by using different methods, such as:

  • direct levelling, where you measure differences in elevation directly. This is the most commonly used method;
  • indirect levelling, where you calculate differences in elevation from measured slopes and horizontal distances.
 
Direct levelling
71.GIF (3736 byte)
     

You have already learned about indirect levelling in Section 5.0, when you learned to calculate differences in elevation from slopes or from vertical angles. Now you will learn about direct levelling.

71b.GIF (2625 byte)

 
Indirect levelling
71a.GIF (5429 byte)

What are the kinds of direct levelling?

5. By direct levelling, you can measure both the elevation of points and the differences in elevation between points, using a level and a levelling staff (see Chapter 5). There are two kinds of direct levelling:

6. In differential levelling , you find the difference in elevation of points which are some distance apart (see Section 8.1). In the simplest kind of direct levelling, you would survey only two points A and B from one central station LS. But you may need to find the difference in elevation between:

7. In profile levelling , you find the elevations of points placed at short measured intervals along a known line, such as the centre-line of a water supply canal or the lengthwise axis of a valley. You find elevations for cross-sections with a similar kind of survey (see Section 8.2).

8. You can also use direct levelling to determine elevations for contour surveying (see Section 8.3), and for setting graded lines of slope(see Section 6.9), where you need to combine both differential levelling and profile levelling.

Differential levelling
72.GIF (11290 byte)

 
Profile levelling
72a.GIF (5321 byte)

9. There are several simple ways to determine the elevations of ground points and the differences in elevation between ground points. You will use a level and a levelling staff with these methods. In the following sections, each method is fully described to help you choose between them. Table 10 will also help you to compare the various methods and to select the one best suited to your needs in each type of situation you may encounter.

 TABLE 10
Direct levelling methods

Section
Type
Method
Suitability
Remarks
Differential levelling
Open traverse
Long, narrow stretch of land
Check for closing error
Differential levelling
Closed traverse
Perimeter of land area and base line for radiation
Check for closing error.
Combine with radiating
Differential levelling
Square-grid
Small area with little vegetation
Squares 10 to 20 m and 30 to 50 m
Differential levelling
Radiating
Large area with visibility
Combined with closed traverse
Longitudinal profile levelling
Open traverse
Non-sighting and sighting level
Check for closing error
Cross-section profile levelling
Radiating
Sighting level with visibility
 
Contouring
Direct
Detailed mapping of small area with a sighting or a non-sighting level and target levelling staff
Slow and accurate.
Progress uphill
Contouring
Square-grid
Small area with little vegetation Especially if perimeter has been surveyed. Small to medium scale mapping
Terrain, scale and accuracy depend on contour interval.
Progress uphill.
Suitable for plane-tabling
Contouring
Radiating
Small to medium scale mapping of large area
Fast and fairly inaccurate. Progress uphill.
Suitable for plane-tabling
Contouring
Cross-sections
Preliminary survey of a long and narrow stretch of land
Fast, fairly inaccurate. Progress uphill.
Suitable for plane-tabling

8.1 How to level by differential

What is differential levelling?

1. You can best understand differential levelling by first considering only two points, A and B , both of which you can see from one central levelling station, LS .

  • Sight with a level from LS at the levelling staff on point A. The point where the line of sight meets the levelling staff is point X. Measure AX. This is called a backsight (BS).
 
Find AX with a backsight
74.GIF (3779 byte)
     
  • Turn around and sight from LS at the levelling staff on point B. The point where the line of sight meets the levelling staff is point Y. Measure BY. This is called a foresight (FS).
 
Find BY with a foresight
 74a.GIF (5486 byte)
     
  • The difference in elevation between point A and point B equals BC or (AX- BY) or (backsight BS - foresight FS).
 
The difference in elevation between
points A and B equals AX minus BY

74b.GIF (5383 byte)
     
  • If you know the elevation of A, called E(A), you can calculate the elevation of B, called E(B), as BS -FS + E(A).
  • But BS + E(A) = HI, the height of the instrument or the elevation of the line of sight directed from the level.
 
75.GIF (9967 byte)
     
  • Therefore,

E(B) = HI - FS


(the elevation at point B being equal to the height of the levelling instrument, minus the foresight).
 
75_a.GIF (8892 byte)

What are backsights and foresights?

It is important for you to understand exactly what "backsight" and "foresight" are in direct levelling.

2. A backsight (BS) is a sight taken with the level to a point X of known elevation E(X), so that the height of the instrument HI can be found. A backsight in direct levelling is usually taken in a backward direction, but not always. Backsights are also called plus sights (+ S), because you must always add them to a known elevation to find HI.

HI = BS + E(X)

 
76.GIF (8366 byte)
     

3. A foresight FS is also a sight taken with the level, but it can be on any point Y of the sight line where you have to determine the elevation E(Y). You will usually take it in a forward direction, but not always. Foresights are also called minus sights (-S) , because they are always subtracted from HI to obtain the elevation E of the point. Remember:

E(Y) = HI- FS

 
76a.GIF (8355 byte)
     

Surveying two points with one turning point

4. Often you will not be able to see at the same time the two points you are surveying, or they might be far apart. In such cases, you will need to do a series of differential levellings . These are similar to the type explained above, except that you will use intermediate temporary points called turning points (TP).  
77.GIF (6189 byte)
     
5. You know the elevation of point A, E(A) = 100 m, and you want to find the elevation of point B, E(B), which is not visible from a central levelling station. Choose a turning point C about halfway between A and B. Then, set up the level at LS1, about halfway between A and C.  
78.GIF (4719 byte)
     
6. Measure a backsight on A (for example, BS = 1.89 m). Measure on C a foresight FS = 0.72 m. Calculate HI = BS + E(A) = 1.89 m + 100 m = 101.89 m. Find the elevation of turning point C as E(C) = HI-FS = 101.89 m - 0.72 m = 101.17 m.  
78a.GIF (7641 byte)
     
   
78b.GIF (8669 byte)

7. Move to a second levelling station, LS2, about halfway between C and B. Set up the level and measure BS = 1.96 m, and then FS = 0.87 m. Calculate HI = BS + E(C) = 1.96 m + 101.17 m = 103.13 m. 0btain E(B) = HI- FS = 103.13 m - 0.87 m = 102.26 m.

8. You can make the calculations more easily if you record the field measurements in a table , as shown in the example. You will not make any intermediate calculations. All BS's and all FS's must be added separately. The sum FS is subtracted from the sum BS to find the difference in elevation from point A to point B.

  • A positive difference means that B is at a higher elevation than A.
  • A negative difference means that B is at a lower elevation than A.
 
79.GIF (10500 byte)
     

Knowing the elevation of A, you can now easily calculate the elevation of B. In this case, E(B) = 100 m + 2.26 m = 102.26 m; this is the same as the result in step 7, which required more complicated calculations. This kind of calculation is called an arithmetic check.

Example
Table form for differential levelling with one turning point.

GR000931.JPG (16836 byte)

 
79_a.GIF (10744 byte)

Surveying two points using several turning points

9. Often you will need to use more than one turning point between a point of known elevation and another point of unknown elevation. To do this, you can use the procedure you have just learned, but you will need to record the field measurements in a table to make calculating the results easier.

10. Knowing the elevation of point A, you need to find the elevation of B. To do this, you need for example  five turning points , TP1 ... TP5, and six levelling stations, LS1 ... LS6.

Note : the turning points and the levelling stations do not have to be on a straight line, but try to place each levelling station about halfway between the two points you need to survey from it.

11. From each levelling station, measure a backsight (BS) and a foresight (FS) , except:

 

Example
Table form for differential levelling with several turning points.
79b.JPG (20725 byte)

Using step 8 as a guideline, enter all measurements in a table and calculate the results as shown in the example below. You will find that point B is 2.82 m higher than point A and, therefore, that its elevation is E(B) = 100 m + 2.82 m = 102.82 m.

12. Even if you are careful, you may still make mistakes when you make your arithmetic calculations from the table. To reduce this kind of error, add two additional columns to your table that will make checking your calculations easy. In these columns, enter the difference (BS- FS), either positive (+ ) or negative (-), between the measurements you took at each levelling station. For example, from LS1 you measure BS (A) = 1.50 m and FS (TP1) = 1.00 m. The difference 1.50 m- 1.00 m = 0.50 m is positive, and you enter it in the (+) column on the TP1 line.

The arithmetic sum of these differences should be equal to the calculated difference in elevation D(E) = +2.82 m. These columns will also help you to calculate the elevation of each turning point , and to check on the elevation of point B more carefully.

Example
Differential levelling with several turning points
81a.JPG (28718 byte)


Making topographical surveys by straight open traverses

13. By now, you have learned enough to make a topographical survey of two distant points by measuring the horizontal distance between them and the difference in their elevation.

When you survey a future fish-farm site, you will use a very similar method. You can then prepare a topographic map of the site (see Chapter 9), which will become a useful guide for designing the fish-farm.

14. This is a survey method using straight open traverses , that is, several intermediate stations along one straight line. You know for example the elevation of starting point A, E(A) = 63.55 m. You want to know the distance of point B from point A, and its elevation. Because of the type of terrain on which you are surveying, you cannot see point B from point A, and you need two turning points , TP1 and TP2 , for levelling. Measure horizontal distances as you move forward with the level, from point A toward point B; try to progress along a straight line. If you cannot, you will need to use the broken open traverse survey method, which involves measuring the azimuths of the traverse sections as you move forward and change direction (see step 17).

 
83.GIF (16537 byte)

15. Set out a table like the one in step 12, and add two columns to it for horizontal distances. Enter all your distance and height measurements in the main part of the table. Then, in the first additional column, record each partial distance you measure from one point to the next one. In the second column, note the cumulated distance , which is the distance calculated from the starting point A to the point where you are measuring. The last number in the second column will be total distance AB.

Example
Topographical survey of a straight open traverse by differential levelling
84b.JPG (25978 byte)

16. Conclusions . Point B is 1.55 m higher than A and its elevation is 65.10 m. It is 156.5 m distant from point A. The arithmetic check from the (BS- FS) differences agrees with the calculated difference in elevation.

Making topographical surveys by broken open traverses

17. Remember, that if you survey by broken open traverses (or zigzags), you will also have to measure the azimuth of each traverse section as you proceed, in addition to distances and elevations.  
84.GIF (3266 byte)
     

18. You need for example to survey open traverse ABCDE from known point A. You require four turning points, TP1, TP2, TP3 and TP4. You want to know:

  • the elevations of points B, C, D and E;
  • the horizontal distances between these points;
  • the position of each point in relation to the others, which will help you in mapping them.
 
84a.GIF (4426 byte)
     
84c.GIF (19995 byte)

Proceed with the differential levelling as described earlier, measuring foresights and backsights from each levelling station. Measure azimuths and horizontal distances as you progress from the known point A toward the end point E. All the azimuths of the turning points of a single line should be the same. This will help you check your work.  
86.GIF (5119 byte)
     
19. Make a table similar to the one shown in step 15, and add three extra columns to it for recording and checking the azimuth values. Enter all your measurements in this table. At the bottom of the table, make all the checks on the elevation calculations, as you have learned to do them in the preceding steps.  
86a.GIF (7739 byte)
     

Example

Topographical survey of a broken open traverse by differential levelling
86b.GIF (43177 byte)


Checking on levelling errors

20. Checking on the arithmetic calculations does not tell you how accurate your survey has been. To fully check on your accuracy, level in the opposite direction , from the final point to the starting point, using the same procedure as before. You will probably find that the elevation of point A you obtain from this second levelling differs from the known elevation. This difference is the closing error .    
88.GIF (5987 byte)
     

Example

From point A of a known elevation, survey by traversing through five turning points, TP1 ... TP5, and find the elevation of point B. To check on the levelling error, survey by traversing BA through four other turning points, TP6 ... TP9; then calculate the elevation of A. If the known elevation of starting point A is 153 m, and the calculated elevation of A at the end of the survey is 153.2 m, the closing error is 153.2 m - 153 m = 0.2 m.

 
88b.GIF (4522 byte)
     
   
88a.GIF (4749 byte)

21. The closing error must be less than the permissible error, which is the limit of error you can have in a survey for it to be considered accurate. The size of the permissible error depends on the type of survey (reconnaissance, preliminary, detailed, etc.) and on the total distance travelled during the survey. To help you find out how accurate your survey has been, calculate the maximum permissible error (MPE) expressed in centimetres , as follows: